project area map

Construction between Rabbit Hill Road and Whitemud Drive started in spring 2021 and was completed in 2024.

Stage One Construction Complete - Spring 2024

Construction on Stage One is now complete. Work started in 2021 and was completed in spring 2024.

Upgrades included:

  • Widening between Haddow Drive and Rabbit Hill Road
  • Adding a shared-use path along the east side of the corridor, along with pedestrian lighting
  • Landscaping, including soil placement, tree replacements, new boulevard trees on cross streets and the addition of naturalized grasses

Terwillegar Drive Expansion - Stage One Project Display Boards

About the Project

Stage One of the Terwillegar Drive Expansion Program includes all road upgrades to Terwillegar Drive from Anthony Henday Drive to Whitemud Drive. The improvements include:

  • Four lanes in each direction (3 for motor vehicles and 1 dedicated lane for transit.
  • Intersection upgrades, including new left and right turning lanes and shared-use path crossings
  • Bus stop upgrades, including longer pull outs, weather-protected shelters, connections to the shared-use path and lighting
  • Shared-use path on the east side of Terwillegar Drive including connections to the communities and lighting
  • Continued landscape naturalization and additional tree plantings

A noise study was completed which revealed that the current berms and fences along Terwillegar Drive provide sufficient noise mitigation to meet the requirements of the Urban Traffic Noise Policy C506A under both current and future traffic conditions. Additional noise reduction measures are therefore not planned as part of Stage One.

Funding

Stage One is funded by the City of Edmonton through the 2019-2022 Capital Budget and in partnership with the Government of Alberta:

  • North portion (Rabbit Hill Road to Whitemud Drive): City of Edmonton
  • South portion (Anthony Henday Drive to Rabbit Hill Road), shared-use path: Province of Alberta

Project Timeline

Project lifecycle with operate highlighted

2021-2023

2020-2021

2017-2020

Project History

The project history provides background information including plans and public engagement activities that were available to finalize the plans for Stage One.

Spring 2023 - Construction Update

Let's Talk Construction

Construction on Stage One over the next year includes:

  • Widening between Haddow Drive and Rabbit Hill Road
  • Adding a shared-use path along the east side of the corridor, along with pedestrian lighting
  • Landscaping including soil placement, tree replacements, new boulevard trees on cross streets and the addition of naturalized grasses

During construction, 2 lanes of traffic will remain open in each direction during peak periods only. No major detours will be required, however, there will be traffic flow impacts during off-peak hours.

Learn More:

April 2022 - Pre-construction Information Session

An online information session was held in April 2022 to provide details about this year’s construction work.

2022 Construction Presentation 
Q&A on 2022 construction plans

April 2021 - Pre-construction Information Session

Thank you for joining the online information sessions for Stage One construction details held on April 15 and 17, 2021. Participants were able to ask questions to the project team and also viewed the Stage One Final Design and this year’s construction details.

Event Materials:

February 2021 - Project Update

Construction for Stage One upgrades begins this year. Site preparation for the new shared-use path will begin in early March with the selective removal of some trees along Terwillegar Drive, from 40 Avenue to Whitemud Drive. Preserving the natural area along Terwillegar Drive is a key component to this project. New trees will be planted where possible once construction is complete.

Roadway construction will begin this spring between Whitemud Drive and Rabbit Hill Road. During construction, 2 lanes of traffic will remain open in each direction. No major detours will be required, however there will be traffic flow impacts during off-peak hours. Once road construction between Whitemud Drive and Rabbit Hill Road is complete, construction for the shared-use path will begin.

Pre-construction work between Anthony Henday Drive and Rabbit Hill Road is anticipated to start summer 2021. More information will be provided prior to construction starting including any detours and construction details.

September 2019 - Public Information Session

Thank you to everyone who joined the September 18 public information session at St. Thomas More Parish to view the recommended concept plan for Stage One. Project staff were available to answer any questions as residents learned more about the updates for transit users, motorists, pedestrians and cyclists, as well as next steps.

An overview of the event is presented in the Public Information Event Summary.

Event Materials:

Intersection Concept Plans:

At the information session, a video was available that showed the new movement along Terwillegar Drive including the dedicated bus lane, motor vehicle lanes and shared-use path.

November and December 2018 - Public Engagement

In November and December 2018, the City hosted 2 public engagement events to share the draft expressway plan. Previous feedback was used in the development of the draft plan and provided input on the plans for transit, pedestrians and cyclists.

A summary of the second phase of engagement is presented in the What We Heard Report.

Event Materials:

November 2017 to February 2018 - Public Engagement

The initial phase of public engagement was designed to gather priorities and perspectives for the City to consider in the validation and updating of the approved concept for Terwillegar Drive, and to gather feedback and perspectives on several high-level freeway configuration solutions and interchange design options. Engagement activities were conducted with community organizations, area residents, businesses, the public and commuters.

On January 24, the City held a public meeting to engage with residents, businesses, communities, and other interested groups during the initial steps of the study. Attendance was high with over 480 interested residents taking this opportunity to share priorities and perspectives for the study, and to share input on draft freeway design options.

A summary of the initial phase of engagement is presented in the What We Heard report.

Meeting Materials:

North Section:

Central Section:

South Section:

Muttart Conservatory in Summer

Building Edmonton

An interactive map with details about the project schedule, phase of delivery and budget on capital projects across the city.

Contact Us

Terwillegar Drive Expansion Program Team

Email  terwillegardrive@edmonton.ca