You’re Invited!
Pre-construction Public Information Event
Thursday, April 16, 2026
4:30 - 7:30pm (Drop-in)
Joan Carr Catholic School
1140 Keswick Drive SW
Information materials will be posted following the event.
Main page content begins here
Upgrades to the Whitemud Drive/Terwillegar Drive interchange are a part of the Terwillegar Drive Expansion Program.
Thursday, April 16, 2026
4:30 - 7:30pm (Drop-in)
Joan Carr Catholic School
1140 Keswick Drive SW
Information materials will be posted following the event.
Stage Two is nearing completion. Construction on the westbound Rainbow Valley Bridge is now complete. Traffic has been shifted to the completed bridge to accommodate ongoing work on the eastbound Rainbow Valley Bridge, which is expected to be finished in 2026.
Work continues across the corridor to improve traffic flow, transit reliability and active transportation connections.
Several interchange improvements on Whitemud Drive/Terwillegar Drive have been completed, including:
Additional interchange work includes:
Active transportation improvements:
Transit improvements:
As part of the project, the retaining walls are complete and the noise wall (southbound Whitemud Drive, 47A Avenue to 45 Avenue) was completed in 2025.
Stage Two consists of Terwillegar Drive and Whitemud Drive Interchange upgrades including major construction on Rainbow Valley Bridge and the widening of Whitemud Drive. Construction is underway to alleviate congestion, accommodate current and planned transit services, and enhance existing active transportation connections to provide all users with a safe and efficient route.
Stage Two is funded by the City of Edmonton through the 2019-2022 Capital Budget and in partnership with the Government of Alberta.
Anticipated completion on:
Anticipated construction progress on:
Anticipated construction progress on:
Construction progress on:
Detailed design (with public information opportunities)
Concept planning and preliminary design
Public engagement opportunities occurred in 2021
Construction is underway to alleviate congestion, accommodate current and planned transit services and enhance existing active transportation connections to provide all users with a safe and efficient route.
Construction continues on the Rainbow Valley Pedestrian Bridge. Construction on the bridge began in the summer of 2023 and is anticipated to be completed in spring 2026. The bridge will allow users to access nearby nature trails and communities while providing a safe crossing for those who walk, cycle and roll.
Construction on the westbound Rainbow Valley Bridge is now complete. Work continues on the eastbound Rainbow Valley Bridge, and is expected to be completed in 2026. View the construction map. Stage 2 is anticipated to be completed in 2026. This includes both pedestrian bridges, the eastbound Rainbow Valley Bridge, paving, center barrier installation and overhead signage. Additional information will be shared in early 2026. Final landscaping will be completed in 2027.
Construction is underway to alleviate congestion, accommodate current and planned transit services, and enhance existing active transportation connections to provide all users with a safe and efficient route. Stage two construction will continue through 2025 and is anticipated to be completed in 2026.
During construction, Whitemud Drive will have two lanes open in each direction during peak hours.
Construction on Stage Two continued through 2024 making progress in enhancing safety, accessibility and traffic flow along Terwillegar Drive.
Construction to widen Rainbow Valley Bridge to 4 lanes in each direction began in early 2024.
The westbound lanes have been closed with two-way traffic redirected onto the eastbound lane.
During construction, 2 lanes on Whitemud Drive will remain open in each direction during peak hours, with additional partial closures expected during off-peak hours as necessary. The existing sidewalk will be removed, and a new pedestrian/cyclist bridge will be constructed, ensuring improved safety for people using active modes of transportation.
Work on the westbound bridge is anticipated to be completed in late spring 2025. Once the westbound bridge is complete, work will begin on the eastbound bridge in 2025. Both bridges are anticipated to be in service by late 2025.
Additional construction information will be shared as work continues in 2025.
View larger image
Access to Snow Valley and the Rainbow Valley Campground will be maintained throughout the project. Pedestrians and cyclists will be temporarily routed through Whitemud Creek ravine during construction.
Construction Bulletin - February 2024
A session to inform the public and provide detailed information was hosted in December 2023.
Terwillegar Drive is being upgraded to ensure this key north-south route continues to connect Edmontonians now and into the future. Construction is underway to alleviate congestion and provide all users with a safe and efficient route.
Stage Two consists of Terwillegar Drive and Whitemud Drive Interchange upgrades, major construction on Rainbow Valley Bridge and the widening of Whitemud Drive. Construction will continue into 2024.
A significant traffic pattern change is required on Whitemud Drive across the Rainbow Valley Bridges. Starting in early 2024, westbound traffic will be moved onto the eastbound bridge. Additional construction information will be shared in early 2024.
Construction for the Terwillegar Drive Expansion includes widening Whitemud Drive between Terwillegar Drive and 122 Street, and the rehabilitation and widening of the Rainbow Valley Bridges. The rehabilitation and widening of the Rainbow Valley Bridges began in May 2023.
During construction, 2 lanes of traffic will remain open on Whitemud Drive in each direction during peak periods. There will be traffic flow impacts during off-peak hours.
Site preparations began in January with the removal of trees along Whitemud Drive. Trees are a highly valued asset and are only removed when all other preservation options are not possible. As part of the Urban Forest Management Plan, the City will plant new trees and shrubs in the project area once construction is complete.
Learn more:
View Display Boards (15MB) from the April 2023 information session
Spring 2023 Newsletter
In November and December 2021, the City hosted 2 public engagement events to share the preliminary design.
Your input will be considered alongside City plans and policies as well as technical requirements as the design and construction plans for Stage Two are finalized.
Learn more about the project:
As part of the public engagement process, we are committed to reporting back on how your input was collected and used. A report detailing What We Heard during this phase of public engagement is now available.