Starting July 13, northbound traffic from the CPKC Railway grade separation to 90A Avenue will be reduced to one lane. This restriction, along with a temporary closure of the right turn from northbound 50 Street to eastbound 90 Avenue, will remain in place until early August to accommodate bus pad and traffic signal construction. Motorists are asked to follow posted signage and use 90A Avenue as a detour.
Pedestrian access along 50 Street will be maintained until the project is fully complete.
Project Update - Summer 2026
- Pedestrian access along 50 Street will be maintained until the project is fully complete.
- Southbound overpass construction is complete, and the overpass is now open to traffic. Southbound traffic that was previously using the split northbound overpass has been transitioned to the new southbound overpass. Both the northbound and southbound overpasses now accommodate two through lanes and one dedicated turning lane.
- Construction and paving of 84 Avenue have been completed. The roadway is scheduled to open to the public in fall 2026. Currently, it’s supporting site access to complete the remaining abutment and pier finishing work.
- Construction of the pedestrian facilities is ongoing, including the multi-use path on the east side and the sidewalk on the west side of 50 Street over the CP rail tracks on both the northbound and southbound overpasses.
- Landscaping will be completed after the pedestrian facilities are finished.
Pedestrian access
Fall 2025 newsletter
About the Project
50 Street provides access to adjacent developing industrial areas and functions as a major north-south commuter and goods movement corridor. Currently, the at-grade Canadian Pacific (CP) railway crossing along 50 Street, north of Sherwood Park Freeway, is identified as the City’s top priority location for grade separation based on delays, traffic impact, frequency of train crossings and other factors.
With ongoing development along 50 Street, particularly along the industrial and residential areas south of Sherwood Park Freeway, traffic volumes and congestion at this crossing will continue to increase. The 50 Street widening and railway grade separation will:
Widen 50 Street to a 6 lane divided roadway between Sherwood Park Freeway and 90 Avenue
Create an overpass for vehicles and active transportation over the rail crossing
Construct a shared-use path on the east side of 50 Street
Upgrade the sidewalk on the west side of 50 Street
Construction between Sherwood Park Freeway and 90 Avenue started in 2022. The project is expected to be complete by the end of 2026.
Sherwood Park Freeway to 76 Avenue
Reconstruction of 50 Street from Sherwood Park Freeway to 76 Avenue has also been identified. This work will include widening 50 Street to a 6-lane divided roadway, including the shared-use path and sidewalks, relocation of overhead utilities and replacement and widening of the existing 50 Street bridge over Sherwood Park Freeway. This area is currently unfunded and will not be constructed with the north part of 50 Street.