A streetcar on the High Level Bridge

The High Level Bridge will undergo targeted minor rehabilitation to ensure the bridge continues to operate safely until its eventual replacement.

The High Level Bridge will undergo targeted rehabilitation, maintenance and monitoring to ensure the bridge continues to operate safely while long-term planning for its eventual replacement advances. This work will focus on maintaining safe operations, extending the bridge’s service life and improving safety and accessibility where possible.

The east sidewalk on the High Level Bridge, from the north end to the southeast staircase, reopened on July 17. The sidewalk from the southeast staircase to Saskatchewan Drive will remain closed until further notice.

EPCOR Work Notice: September 2026

Starting on or about September 21, EPCOR will be installing new storm drainage pipes and infrastructure on 109 Street NW. This work was identified as required by EPCOR following the significant rainfall events in June which identified non-functioning storm drainage pipes in the area. Work to restore proper drainage to the area is expected to last nine weeks.

During construction, the west entrance to the High Level Bridge (near Ezio Faraone Park) will be temporarily closed to traffic. The bridge will still be accessible to traffic from the east side of 109 Street and 97 Avenue NW. Traffic entering the bridge from the east side of 109 Street will still be able to use both lanes of traffic once on the bridge. The sidewalk is expected to remain open for pedestrian access, but there may be limited temporary closures as needed for EPCOR to safely complete the work.  

  

About the Project

The High Level Bridge was constructed by the Canadian Pacific Railway between 1910 and 1913. The railway company transferred ownership of the structure to the City of Edmonton in 1994.

Today, the bridge accommodates approximately 24,000 to 27,000 southbound vehicles daily, as well as pedestrians, cyclists and the High Level Bridge Streetcar. The bridge is a designated Municipal Historic Resource.

Over its more than 100 years of service, the bridge has undergone multiple repairs, maintenance activities, and structural modifications. As planning and design for a larger rehabilitation program advanced, detailed technical investigations determined that the bridge requires significantly more extensive rehabilitation work than originally anticipated.

The City is now advancing a phased approach that includes targeted rehabilitation, proactive maintenance and enhanced monitoring to ensure the bridge remains safe and operational while long-term planning for an eventual replacement bridge progresses.

Future planning will consider opportunities to honour the historical significance of the bridge while supporting the City’s long-term transportation, accessibility and growth needs.

Information will be shared on the minor rehabilitation as work progresses, with construction anticipated to begin in 2028. 

Project Timeline

Project lifecycle chevron with strategy highlighted

Late 2030s

2031-2036

2028

2024-2027

downtown construction

Downtown Construction