The beverl Brdige from the south side looking east

Rehabilitation work on the Beverly Bridge is complete. This project extended the bridge’s lifespan and improved safety for all users.

Project Complete!

Rehabilitation work on the Beverly Bridge was completed in late October 2026. Both sidewalks and all traffic lanes are now open.

Rehabilitation work included repairs to the bridge deck, bridge girders and other bridge components, traffic-barrier replacement and updates to the waterproofing system. Some deficiencies will be addressed in 2027, and the bridge may require lane closures for a short time. 

The City thanks everyone for their patience and cooperation during construction.

Project Overview

To extend its service life and enhance safety, rehabilitation construction on the Beverly Bridge began in 2025. This work included repairs to the concrete deck and steel girders, new pavement and traffic barriers, and miscellaneous other minor repair work on the bridge and approach roadway.

To minimize traffic impacts, construction took place in two stages, with Stage 1 occurring in 2025 and Stage 2 in 2026. Construction was completed in late October 2026. Some minor outstanding deficiencies will be fixed in 2027, which may require lane closures for a short time.

Work included:

  • Bridge deck repair
  • Waterproofing
  • Deck paving
  • Bearing and abutment repair
  • Removal and replacement of barriers
  • Steel girder repairs
  • Upgraded street lighting
  • Miscellaneous concrete repairs

Project Area: Beverly Bridge Rehabilitation

Project Timeline

Project lifecycle diagram with the Operate phase highlighted.

2027 

  • Deficiency work

2026

  • Stage 2 construction

2025

  • Stage 1 construction

Project History

Project Update - March 2026

Construction resumed on the Beverly Bridge Rehabilitation in April. Construction moved to the bridge’s north side and reduced the bridge to two lanes.

Project Update - November 2025

Rehabilitation work on the Beverly Bridge is underway. Rehabilitation will take approximately two construction seasons and is expected to be completed by the end of 2026. Construction work will be done in two phases to minimize traffic impacts. 

Stage 1 began in 2025 on the south side of the bridge. Construction was completed in November 2025 and included:

  • Concrete bridge deck repair
  • Waterproofing
  • Deck paving
  • Bridge girder, bearing and abutment repair
  • Upgraded street lighting 

The bridge has now reopened to 3 lanes of traffic for the winter season.

Stage 2 starts in 2026 and includes work on the north side of the bridge. The bridge will be temporarily reduced to two lanes while this work is underway. Pedestrian access to the trail under the bridge will remain open during construction. To ensure the safety of pedestrians, hoarding will be installed during overhead work.