Fort Road Widening Project Area

Check out this map showing the proposed road changes.

Proposed Changes

Fort Road

The project includes the widening of Fort Road to 6 lanes from Yellowhead Trail to 66 Street. Additional changes include:

  • Widening of the CN Rail underpass 

  • Increased CN Rail underpass clearance by lowering Fort Road

  • New shared-use path on the west side of Fort Road

  • Improved sidewalk on the east side of Fort Road

125 Avenue

A new industrial collector road from 61 Street to 71 Street, west of Fort Road, will be constructed including a new shared-use path and sidewalk.

Fall 2020 Engagement Update

Thank you for talking with us.

Your valuable input has helped shape the Fort Road Widening project's design plan and helped us better understand the needs of all Yellowhead Trail area road network users, area residents, and businesses.

Between October and November 2020, we presented a preliminary design plan and engaged with people to gather their feedback to help adjust and finalize this plan. We engaged with stakeholders, answered questions during online sessions and received your feedback through an online survey. The project team has reviewed and adjusted elements of the plan based on your input. As part of the public engagement process, we are committed to reporting back on how your input was collected and used.

What We Heard

Project Timeline

project life cycle chevron

2021

We have now completed design plans for Fort Road and 125 Avenue. Construction is scheduled to start in spring 2021 and is expected to take 3 years to complete.

Please stay tuned for the pre-construction information session planned for spring 2021.

View the final design plan for Fort Road and 125 Avenue.

2020

Preliminary design and public engagement took place.

View the developed design plan for Fort Road and 125 Avenue.

2019-2020

Design work, including concept plan review, to confirm design meets current standards and freeway conversion goals.

View refined concept maps:
Fort Road
125 Avenue

Yellowhead Trail Is Changing

Stay informed with program updates and opportunities to have your say in shaping the new Yellowhead Trail.

Public Engagement

The City values public input and recognizes its importance in identifying the needs of all Yellowhead Trail road users, area residents and businesses. Each segment of the Yellowhead Trail Freeway Conversion Program is being built to balance the roadway requirements with community, business and commuter needs. See Program History to learn more.

Please contact us with your Fort Road Widening questions by emailing yellowhead@edmonton.ca.

For More Information

Yellowhead Trail Freeway Conversion

Telephone

311

Email yellowhead@edmonton.ca

End of page content. Please choose between the following five options:

Back to main menu Back to current page menu and content View current page breadcrumb Back to site search Continue to page footer content