Roof Truss Engineering Requirements for New Construction Building Permits
Effective March 1, 2026, applicants must provide roof truss assemblies authenticated by an Alberta-licensed engineering professional with the building permit application. This includes all Part 9 Buildings, such as single-family or semi-detached homes, and 3- and 4-unit row houses.
For more information, review the Policy Bulletin B23-03 Roof Truss Engineering Requirements.
These permits are applicable to non-residential (commercial, industrial, institutional, and similar buildings), large-scale residential (apartments, row houses with 5 or more principal units), mixed-use (a mix of residential and non-residential) developments, Cluster Housing Project, that includes 2 or more residential buildings excluding Backyard Housing, temporary structures such as storage sheds and sea cans.
For alterations and additions, see Changes to Existing Commercial Buildings.
Which Permits Do I Need?
All projects require:
- Development Permit (Zoning Approval) ensures your building and structures (including temporary structures) are allowed in your location and comply with the Zoning Bylaw
- Building Permit to audit project design and construction in accordance with Alberta Safety Codes Act. Building Permit provides permission to begin construction. Starting construction without all permits can result in stop work orders, fines and/or administrative penalties.
- Trades Permits for heating and ventilation, plumbing, gas, and electrical work
- Sign Permit if installing exterior signs on your site
Preparation for the Application
You can identify the zone and any applicable overlays of your site using the interactive zoning map.
Also refer to the Specific Development Regulations in the Zoning Bylaw to understand additional requirements related to your specific uses.
Use the GeoDiscover Alberta Map to determine whether abandoned wells are located on your property.
Use the Listing of Historic Resources to help determine if there may be a historic resource concern in your proposed project area. For more information on how to receive Historical Resources Act approval for a development project, visit the Government of Alberta’s website.
Pre-application meetings are not required but highly encouraged for new buildings and additions and significant renovations.
Applicants who book pre-application meetings find that meetings shorten development permit review times.
Applications for new buildings, additions and some facade improvements may be subject to review by the Edmonton Design Committee if they are located in designated areas.
The Development Planner will determine whether your project will be subject to review by the Edmonton Design Committee while reviewing your application.
The Edmonton Design Committee reviews and provides recommendations to applicants and the City regarding development applications.
The Development Planner will consider the Edmonton Design Committee's comments before issuing the Development Permit.
For more information, including submission requirements, see Edmonton Design Committee.
If your project involves complex, unique, industrial, commercial, or large-scale residential infill development you may qualify for enhanced service with a Client Liaison.
To learn about qualification criteria and contact information, see Client Liaison.
General Resources
Zoning Bylaw 20001
Historical Land Use Bylaw (see Bylaw Lookup) - Use this when a Direct Control Zone references a previous version of the land use bylaw
Interactive Maps, including the Zoning Map
Zoning Matrix
Plans In Effect
Current Development Permit Applications Map
Signs
City Policies and Guidelines
Policy B23-01 Fire Separation Between Row Houses With More Than Two Secondary Suites
Policy B23-02 Window Opening Control Devices
Policy B19-03 Area Separation Wall (ARCHIVED)
Policy B19-04 Small Building Access Policy
Policy Bulletin B23-03 Roof Truss Engineering Requirements
Transportation Access Management Guidelines
Accessibility Design Guide (for infrastructure and facilities that are owned, operated or leased by the City of Edmonton)
External Agencies
ATCO Gas
EPCOR Water, Sewer, and Waste Management
Service Alberta Land Titles
Subdivision and Development Appeal Board
Safe Excavation Near Pipelines
Alternative Solutions Guide for Point Access Blocks
A Point Access Block is the name for a building with a single staircase as a way to exit the building. This is a common building type around the world. It allows for more flexibility in the floor layout, which can result in more housing units or larger units with 3 or more bedrooms.
Building regulations require a minimum of 2 staircases for residential buildings that are 2 storeys and higher. Under the Alberta Edition of the National Building Code of Canada, a single staircase building can be considered if the developer can demonstrate through an Alternative Solution that the design is just as safe and effective as one with 2 staircases.
The City of Edmonton has created resources that will help developers explore this option. This is part of the City’s efforts to encourage the development of different types of housing at different price points in all neighbourhoods.
Point Access Block Resources:
Development Permit Application
Review the documents required to be submitted in order for your application to be accepted for review.
Additional information may be requested when your application is under review.
Applications are considered incomplete if documents are missing or do not include all information listed in the standards.
Submitting an incomplete application will extend project timelines.
Landscape Plan Standards
Landscape Plan Sample
View more information on landscaping securities and policies.
Must be a current copy, obtained within the past 3 months.
Alberta Land Titles
Restrictive covenants, utility rights-of-way, easements, caveats.
Prepared by an Alberta Land Surveyor within the past 3 months.
Completed form and associated map.
Building Permit Application
Carefully review the application requirements to submit a complete application. The table below lists documents required to begin your application.
Additional information may be requested when your application is under review.
Applications are considered incomplete if documents are missing or do not include information listed in standards.
Submitting an incomplete application will extend application timelines.
| Application Requirement | Minimum Submission Standard and Guide |
|---|---|
| Site Plan | Site Plan Standards |
| Survey Plan | Prepared by a registered Alberta land surveyor Survey Plan Standards |
| Building Plans | Note: Building permit plan standards are different from development permit standards. Building Permit Minimum Drawings and Specifications Requirements |
| Professional Schedules | The requirement for stamped drawings and schedules for National Building Code (Alberta Edition) depends on the project size and complexity. Professional Work Product Authentication must be done in the manner required by the professional’s regulatory body. |
| Energy Code Documents | Energy Code Requirements |
| Geotechnical Report | Prepared by a registered engineering professional |
| Project Implementation Plan (PIP) | PIP Guide PIP Letter of Commitment |
| New Home Warranty | Required for dwellings that will be sold. New Home Buyer Protection Act |
Additional forms:
Variance/Alternative Solutions Request Form
Submitting Your Application
Apply for permits online at SelfServe. The project can then be managed by the permit holder or delegated constructor through the project dashboard.
The permit holder can see the status, respond to more information requests, find reviewed plans and permit documents to have on the job site, add and change trades, initiate the revision process if needed, request all inspections, and track inspection outcomes.
For inquiries and questions, please book a virtual or in-person appointment.
For a complete list of fees see:
Permanent Area Contributions (PAC)
Arterial Roadway Assessments (ARA)
There are several ways to make a payment.
Additional fees may apply. Additional charges may apply for revisions.
After You Apply
City staff will review your application for compliance with the Zoning Bylaw and applicable Safety Codes.
Processing Times
Overall application processing times can be found on the development and construction application processing times web page. Applicants can also check the status of their specific application by visiting their project dashboard in SelfServe.
Building Permit Queue Times
See up-to-date queue times for building permit applications.
More Information Requests
City staff may request additional information at various stages of the Development Permit and Building Permit process. To learn how to reply to a more information request in SelfServe, see the More Information Requested (MIR) Guide.
Permit Teams
To get up-to-date information, ask the permit holder to add you as a team member on the permit application. See the Team Settings Frequently Asked Questions for more information.
To make changes before a Development Permit or Building Permit is issued, consult the City staff assigned to your file.
After a Development Permit or Building Permit is issued, request Permit Revisions in SelfServe. Additional charges may apply for revisions.
To cancel your application, email the Cancellation/Refund Request form to the person who is handling your application.
After your project has progressed to the right stage, you must request that a Safety Codes inspector visit your site.
Failure to complete required inspections may result in you having to remove finished walls and/or additional inspection costs and delays.
All required inspections for a project are listed in SelfServe after issuing a permit. You can request, cancel, or reschedule them there. You can also request inspections by calling 311 (outside Edmonton: 780-442-5311).
Deviation from reviewed plans cannot be endorsed on-site. When work completed does not match the reviewed plans, revised plans must be submitted for additional review.
Review the Commercial Inspections page to learn:
- How to prepare for your inspection by displaying the address, providing safe access and having the reviewed permit documents printed on site for reference by the inspector
- At which stages to request inspections
- How to request inspections
- What to expect during each inspection type