These permits are applicable to non-residential (commercial, industrial, institutional, and similar buildings), large-scale residential (apartments, row houses with 5 or more principal units), mixed-use (a mix of residential and non-residential) developments, Cluster Housing Project, that includes 2 or more residential buildings excluding Backyard Housing, temporary structures such as storage sheds and sea cans.

For alterations and additions, see Changes to Existing Commercial Buildings.

Which Permits Do I Need?

All projects require:

  • Development Permit (Zoning Approval) ensures your building and structures (including temporary structures) are allowed in your location and comply with the Zoning Bylaw
  • Building Permit to audit project design and construction in accordance with Alberta Safety Codes Act. Building Permit provides permission to begin construction. Starting construction without all permits can result in stop work orders, fines and/or administrative penalties.
  • Trades Permits for heating and ventilation, plumbing, gas, and electrical work
  • Sign Permit if installing exterior signs on your site

The typical project process for a new commercial building.

Preparation for the Application

Know Your Site

You can identify the zone and any applicable overlays of your site using the interactive zoning map.

Also refer to the Specific Development Regulations in the Zoning Bylaw to understand additional requirements related to your specific uses.

Use the GeoDiscover Alberta Map to determine whether abandoned wells are located on your property.

Use the Listing of Historic Resources to help determine if there may be a historic resource concern in your proposed project area. For more information on how to receive Historical Resources Act approval for a development project, visit the Government of Alberta’s website.

Pre-Application Meeting

Pre-application meetings are not required but highly encouraged for new buildings and additions and significant renovations.

Applicants who book pre-application meetings find that meetings shorten development permit review times. 

Edmonton Design Committee

Applications for new buildings, additions and some facade improvements may be subject to review by the Edmonton Design Committee if they are located in designated areas. 

The Development Planner will determine whether your project will be subject to review by the Edmonton Design Committee while reviewing your application.

The Edmonton Design Committee reviews and provides recommendations to applicants and the City regarding development applications.

The Development Planner will consider the Edmonton Design Committee's comments before issuing the Development Permit.

For more information, including submission requirements, see Edmonton Design Committee. 

Client Liaison

If your project involves complex, unique, industrial, commercial, or large-scale residential infill development you may qualify for enhanced service with a Client Liaison.

To learn about qualification criteria and contact information, see Client Liaison.

Alternative Solutions Guide for Point Access Blocks

A Point Access Block is the name for a building with a single staircase as a way to exit the building. This is a common building type around the world. It allows for more flexibility in the floor layout, which can result in more housing units or larger units with 3 or more bedrooms.

Architectural rendering of an alternative housing design.
Eye-level rendering illustrating the possible scale and appearance of Design Study 1, Design Guide.

Building regulations require a minimum of 2 staircases for residential buildings that are 2 storeys and higher. Under the Alberta Edition of the National Building Code of Canada, a single staircase building can be considered if the developer can demonstrate through an Alternative Solution that the design is just as safe and effective as one with 2 staircases.

The City of Edmonton has created resources that will help developers explore this option. This is part of the City’s efforts to encourage the development of different types of housing at different price points in all neighbourhoods.

Point Access Block Resources:

Development Permit Application

Review the documents required to be submitted in order for your application to be accepted for review.

Additional information may be requested when your application is under review.

Applications are considered incomplete if documents are missing or do not include all information listed in the standards.

Submitting an incomplete application will extend project timelines.

Building Permit Application

Building Permit Application Requirements

Carefully review the application requirements to submit a complete application. The table below lists documents required to begin your application.

Additional information may be requested when your application is under review.

Applications are considered incomplete if documents are missing or do not include information listed in standards.

Submitting an incomplete application will extend application timelines. 

application requirements
Application RequirementMinimum Submission Standard and Guide
Site PlanSite Plan Standards
Survey PlanPrepared by a registered Alberta land surveyor
Survey Plan Standards
Building Plans

Note: Building permit plan standards are different from development permit standards.

Building Permit Minimum Drawings and Specifications Requirements
All-Gender Washroom Guide NBC2023(AE)
Accessibility Design Guide 2024

Professional Schedules

The requirement for stamped drawings and schedules for National Building Code (Alberta Edition) depends on the project size and complexity. 

Professional Work Product Authentication must be done in the manner required by the professional’s regulatory body.
Schedules of Professional Involvement Forms

Energy Code DocumentsEnergy Code Requirements
Geotechnical ReportPrepared by a registered engineering professional
Project Implementation Plan (PIP)PIP Guide
PIP Letter of Commitment
New Home WarrantyRequired for dwellings that will be sold. 
New Home Buyer Protection Act

Additional forms:
Variance/Alternative Solutions Request Form

Submitting Your Application

Applying Online

Apply for permits online at SelfServe. The project can then be managed by the permit holder or delegated constructor through the project dashboard.

The permit holder can see the status, respond to more information requests, find reviewed plans and permit documents to have on the job site, add and change trades, initiate the revision process if needed, request all inspections, and track inspection outcomes.

Apply online

For inquiries and questions, please book a virtual or in-person appointment. 

Fees

For a complete list of fees see:

Permanent Area Contributions (PAC)
Arterial Roadway Assessments (ARA)

There are several ways to make a payment.

Additional fees may apply. Additional charges may apply for revisions.

After You Apply

Application Processing

City staff will review your application for compliance with the Zoning Bylaw and applicable Safety Codes.

Processing Times

Overall application processing times can be found on the development and construction application processing times web page. Applicants can also check the status of their specific application by visiting their project dashboard in SelfServe.

Building Permit Queue Times

See up-to-date queue times for building permit applications.

More Information Requests

City staff may request additional information at various stages of the Development Permit and Building Permit process. To learn how to reply to a more information request in SelfServe, see the More Information Requested (MIR) Guide.  

Permit Teams

To get up-to-date information, ask the permit holder to add you as a team member on the permit application. See the Team Settings Frequently Asked Questions for more information.

Changing or Cancelling Your Application

To make changes before a Development Permit or Building Permit is issued, consult the City staff assigned to your file.

After a Development Permit or Building Permit is issued, request Permit Revisions in SelfServe. Additional charges may apply for revisions.

To cancel your application, email the Cancellation/Refund Request form to the person who is handling your application. 

Requesting Inspections

After your project has progressed to the right stage, you must request that a Safety Codes inspector visit your site.

Failure to complete required inspections may result in you having to remove finished walls and/or additional inspection costs and delays.

All required inspections for a project are listed in SelfServe after issuing a permit. You can request, cancel, or reschedule them there. You can also request inspections by calling 311 (outside Edmonton: 780-442-5311).

Deviation from reviewed plans cannot be endorsed on-site. When work completed does not match the reviewed plans, revised plans must be submitted for additional review.

Review the Commercial Inspections page to learn:

  • How to prepare for your inspection by displaying the address, providing safe access and having the reviewed permit documents printed on site for reference by the inspector
  • At which stages to request inspections
  • How to request inspections
  • What to expect during each inspection type