Project Update - Summer 2026
Ledcor continues to make progress on the pedway project, which will ultimately connect Churchill LRT Station to the Station Lands development north of 104 Avenue. In 2026, a major milestone was reached when the tunnel roof was completed, fully interconnecting all six phases of the pedway underground. The project is anticipated to be complete by the end of 2026.
Work continues inside a section of the existing pedway between Churchill Station and the Edmonton Law Courts. During the closure, crews will install the final electrical, mechanical and architectural finishes.
On August 14, 99 Street and 103A Avenue reopened, along with the majority of the west bike lane on 99 Street. This restored access to the City Hall parkade from both 102A Avenue and 103A Avenue.
In late fall, a portion of 99 Street at 102A Avenue will temporarily close for approximately one month for installation of a roadway contraction joint, which will temporarily change access into the City Hall parkade (access will be maintained from 103A Avenue).
More information can be found in our August project update for impacts on pedestrian, bicycle and vehicular traffic.