Dunluce has been chosen for Neighbourhood and Alley Renewal. Construction is underway.
Construction Update - June 2026
It’s the second year of Dunluce Neighbourhood and Alley Renewal and construction is underway. Work consists of reconstruction and paving of the roads and alleys, removal and replacement of public sidewalk, curb, gutter, street lighting and landscaping.
Front Streets Construction
Please view this scope map to see the 2026 construction area for front streets and alley construction.
The laydown area for the front streets contractor is east of the Dunluce Community Playground. Please also be advised that other contractors will be in the project area adjusting utilities in various locations.
Crews have completed work in the following locations, except for select driveway and walkway tie-ins that require utility repairs or adjustments:
- Sidewalk improvements in the 158 Avenue outer loop between 123 Street NW and 121 Street NW.
- Sidewalk improvements in the 159 Avenue outer loop between 125 Street NW and 121 Street NW.
- Sidewalk improvements along the north side of 157 Avenue between 121 Street and Castledowns Road.
Crews are currently working in these locations:
- Sidewalk improvements in the 158 Avenue inner loop between 123 Street NW and 121 Street NW.
- Sidewalk improvements in the 159 Avenue inner loop between 125 Street NW and 121 Street NW.
- Sidewalk improvements for the 161 Avenue cul-de-sac, west of Dunluce Road
The following are tentatively scheduled to start in June:
- Complete driveway and walkway connections in the inner and outer loops of 158 Avenue and 159 Avenue.
- Sidewalk improvements for 161 Avenue cul-de-sac, east of Dunluce road (East/south side only)
- Sidewalk improvements for 123A Street outer loop from 161 Avenue to 123 Street
- Road reconstruction on 158 Avenue and 159 Avenue loops
- Landscaping contractor anticipated to start
Alley Construction
This scope map numbers the alley Renewal projects. 2026 construction takes place in the northwest corner of the neighbourhood.
Crews have completed paving in alleys 13 and 15, landscaping to follow. Construction in alleys 11, 12 and 14 is underway. All schedules are subject to change. This web page will be updated throughout construction.
Progression of Work
The contractor working for the City has developed a map to show the progression of work, including scheduled closures.
Prepare for Construction
The City of Edmonton and EPCOR are working together to construct Low Impact Development (LID), which will help with stormwater retention and help mitigate flooding.
Please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction.
If no alley access is available and/or you have special access requirements (such as DATS or a temporary access ramp to the front of your home), please contact the Construction Project Manager, Stephen Au, at 780-496-4055 or 311, to coordinate.
Construction in Dunluce is expected to take 5 years (planned completion fall 2029).