Papaschase Industrial Pavement Renewal - August 2026

Construction is underway and is expected to be complete in late fall 2026.

The project includes the removal and replacement of isolated sections of concrete sidewalk, curb and gutter, and commercial accesses, the rehabilitation and repaving of the roadways and minor landscaping restoration.

The first phase of the work entails the isolated repair of concrete curbs, sidewalk and accesses. This portion of the construction will be done in phases working on one side of the road at a time in order to maintain on-street parking. To maintain access to businesses and parking lots, accesses will be reconstructed in two halves, where required.

Concrete repairs in the western half of the project (97–101 Street, 44–48 Avenue) began the week of May 4, 2026, and are now complete. Concrete repairs in the eastern half of the project (93–97 Street, 45–51 Avenue) began in late June and are expected to be completed by mid-August.

Rehabilitation and repaving of the roadways in the western half of the project (97–101 Street, 44–48 Avenue) began in mid-July and is scheduled to be complete by early August. Rehabilitation and repaving of the roadways in the eastern half of the project (93–97 Street, 45–51 Avenue) is scheduled to begin in late August and be complete by late September.

Landscaping restoration for the whole project is scheduled to begin in mid-August and be completed by the end of September. 

Impacted properties received City Construction bulletins in late April 2026, followed by start-up bulletins from the contractor (Park Paving), in early May. The contractor will deliver additional bulletins which will outline their anticipated start dates for each phase of work before the work begins.

Scope Map

Construction Project Manager: David Kavanagh
david.kavanagh@edmonton.ca
780-496-4055

About the Program

As a part of the Neighbourhood Renewal Program, the City will be coordinating road construction in industrial neighbourhoods. Prior to construction starting, property owners will receive a bulletin outlining the estimated start and finish dates and contact information.

Industrial Neighbourhood Renewal consists of road rehabilitation and road reconstruction, depending on the condition of the road. Road rehabilitation includes asphalt overlay, or road reclamation first, then an asphalt overlay. Road reconstruction removes the existing asphalt and road base, and replaces it with a new road base and asphalt paving. Other spot concrete repairs are done as well.