This page is specific to Neighbourhood and Alley Renewal in Glenwood west of 163 Street. See Glenwood (163 Street East) Alley Renewal for information on Alley Renewal east of 163 Street.
Glenwood (163 Street West) has been chosen for Neighbourhood and Alley Renewal. Construction began spring 2025.
During Neighbourhood Renewal construction, some transit routes are being detoured. For more information, visit ETS Alerts and Service Impacts.
Project Update - October 2026
It’s the second year of Glenwood West Neighbourhood and Alley Renewal construction. Work on front streets is scheduled to start in July. Construction on the remaining alleys west of 163 has resumed.
Alley Construction
The 2026 scope of work for Alley Renewal in Glenwood (163 Street West) is complete.
Front Street Construction
Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting.
This year, the majority of front street construction will take place from 163 Street to 165 Street. Work will also happen in the commercial area along 164 Street to 166 Street. Please view this scope map to see the 2026 construction area.
Work is progressing as follows:
- 163 Street - 100 Avenue to 96A Avenue
- Gravel placement for the shared-use path is complete and the forms are set up and ready for concrete. Concrete work is anticipated to be completed the week of October 5. Preparation work for paving the parking bays will start right after.
- 96A Avenue - 163 Street to 165 Street
- Most of the sidewalk work is complete. Crews are currently setting forms and completing the remaining private sidewalk connectors, alley crossings and driveway crossings.
- 99A Avenue and 99 Avenue
- Sidewalk concrete has been poured along 99A Avenue and 99 Avenue near 165 Street. Crews are currently working on the remaining private sidewalk connections.
- 164 Street - South of 99 Avenue and 97 Avenue
- Crews are continuing gravel preparation for the sidewalks. Formwork is expected to begin shortly, and the area should be ready for concrete placement next week.
- 164 Street Industrial
- The east and the west sidewalks are prepared and ready for concrete placement. Road paving is anticipated to begin soon.
- 165 Street Industrial
- Crews are awaiting TWSI panels for the ramps. The TWSI will be installed soon and then concrete can be placed on the ramps and the remaining sections. Following concrete placement, road paving can begin.
- 166 Street Industrial - East Side
- From 100 Avenue to just past the alley, sidewalk forms are set and ready for concrete placement.
Progression of Work
The contractor working for the City has developed a map to show the progression of work, including scheduled closures.
Check out the links below to prepare for construction:
- Glenwood (163 Street West) Neighbourhood and Alley Renewal What We Decided report (21.24 MB)
- What to expect during Alley Renewal construction
The City of Edmonton and EPCOR are working together to construct Low Impact Development (LID), which will help with stormwater retention and help mitigate flooding.
Please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction. If no alley access is available and/or you have special access requirements (i.e. DATS or a temporary access ramp to the front of your home), please contact the Construction Project Manager, Rohail Khan, 780-496-4055, to coordinate.
Construction in Glenwood (163 Street West) began in spring 2025 and is expected to take 3 years (planned completion fall 2027). Neighbourhood and Alley Renewal in Glenwood (163 Street West) is progressing on time and on budget.
Preparing for Construction video
Sign up below to receive news and updates on Glenwood (163 Street West) Neighbourhood and Alley Renewal.
We commit to using your feedback to inform communication during construction.
Garbage and Recycling Collection
While your alley is closed for construction, waste cart collection will occur from your front street or avenue. Residents are asked to temporarily relocate carts and recycle bags to the front of your property during alley closures for pick-up on collection days. Carts and bags should be placed in a visible location along the curb or back of the sidewalk, at which point collection workers will maneuver carts so they can be emptied. We recommend you identify your home address in the space provided on the carts to ensure your assigned carts are returned to your home after collection.