Beverly Heights has been chosen for Alley Renewal. Construction started spring 2024, with anticipated completion in 2026.

Construction Update - August 2026

It’s the third year of Beverly Heights Alley Renewal and construction is underway. Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting.

This scope map numbers the alleys. The following sections have asphalt work complete and are ready for landscaping:

  • Section 7C
  • Section 35
  • Section 37
  • Section 40
  • Section 41
  • Section 42
  • Section 47
  • Section 51
  • Section 53
  • Section 54
  • Section 56

The following sections are still in progress or pending paving work:

  • Section 20: Paving in progress
  • Section 55: Paving is currently in progress.
  • Section 49: Currently on the second lift of gravel installation
  • Section 45: Coring is underway; paving will occur after EPCOR work is completed.
  • Section 7A/B/C: Coring is underway; there is a pending resolution for a catch basin issue.
  • Sections 1, 4, and 5: Drainage scope is complete, but these alleys are pending future work.

Review what to expect during Alley Renewal construction.

For those who live in the 2025 construction areas, the outstanding road deficiency work is scheduled to start at the same time as this year’s construction.

Please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction. If no alley access is available and/or you have special access requirements (such as DATS or a temporary access ramp to the front of your home), please contact the Construction Project Manager, Clinton Mah, 780-496-4055, to coordinate.

Construction in Beverly Heights began in May 2024 and is expected to complete in October 2026. Renewal in Beverly Heights is progressing on time and on budget.

Garbage and Recycle Collection

While your alley is closed for construction, waste cart collection will occur from your front street or avenue. Residents are asked to temporarily relocate carts and recycle bags to the front of your property during alley closures for pick-up on collection days. Carts and bags should be placed in a visible location along the curb or back of the sidewalk, at which point collection workers will manoeuvre carts so they can be emptied.

We recommend you identify your home address in the space provided on the carts to ensure your assigned carts are returned to your home after collection.

About the Project

Alley Renewal involves alley reconstruction and repaving, improvements to surface drainage where possible, and upgrading of existing alley lighting to LED fixtures. It also includes the opportunity for a local improvement to add alley lighting if property owners are interested. Utility assessments and repairs, along with removals and pruning of trees and shrubs, are also completed.

Construction began in spring 2024 and is anticipated to be complete in fall 2026.