A playground

Five parks in the Balwin and Belvedere Neighbourhoods have been selected for revitalization.

Project Update - April 2026

Zoie Gardner Park

Construction in Zoie Gardner Park continues. Work includes:

  • Additional line painting on the basketball court
  • Art mural installation on the utility shack (to be completed summer 2026)
  • Concrete removal and replacement on the north side of the spray park to fix cracking that formed over the winter
  • Installation of street games on the concrete pad on the south side of the spray park
  • Additional repairs and maintenance work to be completed, as required

Sections of the park will be fenced off to complete concrete repairs and install street games. The remainder of the playground will remain open for use during the repairs. This work is expected to be completed in June 2026.

Balwin Park

Construction is set to resume in Balwin Park. Work includes:

  • Construction of the Heart Labyrinth in the southeast corner of the playground on the outside of the new playground pod
  • Concrete removal and replacements to remediate cracks that formed over the winter months
  • Painting touch-ups on the rubber playground surfacing and playground equipment
  • Additional repairs and maintenance work as required

Sections of the playground will be fenced off to construct the Heart Labyrinth and complete concrete repairs and surface painting. The remainder of the playground will remain open for use during the repairs. This work is expected to be complete in June 2026.

Belvedere Park

All construction at Belvedere Park is complete. The basketball court drainage issues have been corrected and all elements of the park are open for use. Additional landscape maintenance and repairs will be completed as required over spring/summer 2026.

About the Project

The project includes the revitalization of five open spaces within the Balwin and Belvedere neighbourhoods with the focus on safety, accessibility, improved and expanded amenities for social connection and passive use, and improved recreation, play, and cultural activities for diverse users.

The project will include the Planning Concept and Design phases for all five park sites.

Preliminary Designs

Balwin

Belvedere

The Belvedere Community League is working on a new public park at 12923 64 Street. That park is not part of this project and more information can be found on the community league's website.

Project Timeline

Project lifecycle with build highlighted

2025

2024

2023

2022

2021

Project History

September 2025 - Project Update

Zoie Gardner Park

Construction on Zoie Gardner Park is nearly complete! The playground and all hard surface construction has been completed. The black rubber surfacing in the playground pod will be completed after the September long weekend, along with the landscaping and site furniture installations.

The new park lighting is expected to be completed by mid-September and the basketball equipment is expected to arrive near the end of September.

After all construction is complete, the construction fencing will remain in place to allow for the new sod and landscaping to establish. The fencing is expected to come down the first week of October. Once fencing is down, the park is open for community members to enjoy.

The washroom building is being remediated and building remediation will continue through the fall and into the winter. This work has no impact on the park opening. A new art mural will be installed on the building in spring 2026. The mural will be reflective of the community diversity and pay tribute to Zoie Gardner and her contributions to the community.

The mural will be installed on the east and west walls. One wall represents the land and the day, while the other represents the night sky. On the land wall, trees rise from the ground, animals wander and water flows through the centre. On the sky wall, the sun and moon appear among stars, with flying creatures, fish and a dragon moving through the night.

Heraa Khan has been selected to design the murals.

Heraa Khan is a Pakistani visual artist currently living and working in amiskwacîwâskahikan, Treaty 6 Territory. She began her artistic journey studying the traditional Indo-Persian practice of miniature painting. Heraa holds a BFA from the National College of Arts in Lahore and an MFA from the University of British Columbia, Canada. Her diverse practice includes painting, drawing, digital animation and film.

Mural representing the land and the day showing trees rise from the ground, animals and water

Mural representing the night sky showing the sun and moon among the stars with flying creatures, fish and a dragon

Balwin Park

Construction on Balwin Park is progressing on schedule and is nearing completion. The playground equipment has been installed, along with the hard surfaces and new trail. The rubber playground surfacing is expected to be completed mid September. Site furniture and park lighting are expected to be completed near the end of September. All landscaping and clean up restorations are expected to be completed by the first week of October.

Because new sod and landscaping are very susceptible to damages from foot traffic, the construction fencing will remain in place for a couple weeks after construction has been completed to allow for the new sod and landscaping to fully establish. Fencing is expected to be removed after the Thanksgiving weekend and the park will be open for use.

The new playground in Balwin Park is the first of its kind in Edmonton. Designed by local artist AJA Louden, shown below, the playground was inspired by nature and science fiction. It was created as a place to play, to grow together and to imagine the future.

New Balwin Park playground showing elements inspired by nature and science fiction

Balwin Park designer AJA Louden sitting in playground element

Belvedere Park

Due to unforeseen drainage issues, the new basketball court required replacement. This work has now been completed. Due to this unexpected work, the overall completion of the park has been delayed to the last half of September. Line painting and basketball equipment installation on the court is expected to be complete by the third week of September, along with final cleanup and landscape restorations.

The City and our contractors would like to thank all residents for their patience and support during the project.

May 2025 - Project Update

Construction on Zoie Gardner Park and Balwin Park is set to begin in May 2025.

Zoie Gardner Park

Construction on Zoie Gardner Park construction will start in June 2025. The park is expected to be closed until September 2025.

The construction area will be fenced for safety and signage will be posted throughout the area.

Construction includes a new walking trail, basketball court, a new playground, new site furniture, park lighting and landscaping. Some trees in the park will be removed to accommodate the new playground. Removals will take place May 2025. Information on construction impacts is available in the construction bulletin.

The existing spray deck will not be changed and is incorporated into the new park design.

The new playground has a safari theme to compliment the spray deck features.

The washroom building will be remediated, and a new art mural will be installed on the building. The mural will be reflective of the community diversity and pay tribute to Zoie Gardner and her contributions to the community.

Graphic showing new safari themed playground for Zoie Gardner Park

Balwin Park

Construction on Balwin Park started in May 2025. Parts of the park are expected to be closed until September 2025.

The construction area will be fenced for safety and signage will be posted throughout the area.

Aerial image showing Balwin Park closures

Construction includes a new walking trail, park lighting, new artist-inspired playground, new site furniture and landscaping.

The playground being built in Balwin Park is the first of its kind in Edmonton. Designed by local artist AJA Louden, the playground was inspired by nature and science fiction. It was created as a place to play, to grow together and to imagine the future.

Image showing Balwin Park playground inspired by nature and science fiction

All existing amenities, including the community hall and parking lot, tennis courts, rink and basketball court, will remain open for use during construction.

Some trees in the existing shrub bed next to the playground will be removed to accommodate the new playground construction.

Information on construction impacts is available in the construction bulletin.

December 2024 - Project Update

Construction in Belvedere Park is nearly complete. The coloured surfacing and painted games will be installed on the new basketball courts and surrounding hard surface areas in spring 2025 along with the new basketball amenities. Construction fencing will remain over the winter to protect the newly planted sod until fully established in spring 2025. Tree pruning will take place around the entire park over the winter to improve sightlines and clear deadwood. Selective tree removals will also be completed to improve sightlines south of the community rink enclosure.

Robert Brett Park - Construction is complete and the park is open for use. Tree pruning will take place around the entire park over the winter to improve sightlines and clear deadwood. Selective tree removals will also be completed to improve sightlines around the new playground.

Balwin Park - Designs for the new playground and park are being finalized and construction is anticipated to begin spring 2025.

Zoie Gardiner Park - Designs for the new park are being finalized and construction is anticipated to begin spring 2025.

April 2024 - Project Update

Construction is expected to begin in Robert Brett Park and Belvedere Park in May 2024. Both parks are expected to be completed by fall 2024.

Robert Brett Park improvements will include the removal and replacement of the play equipment, construction of a new basketball court, new walking trails and park lighting. Belvedere Park improvements will include the replacement of the basketball court, a new plaza area and walking trails complete with park lighting.

Residents can expect to see construction traffic (excavators, dump trucks and other equipment) and the park areas will be secured with fencing for the duration of construction. Construction will take place during normal working hours (7am-7pm) Monday through Friday with some Saturday work. Please adhere to all construction signage during the project.

November 2023 - Project Update

Construction in Braids Park is now complete! Thank you for your patience as City crews worked to improve the walking paths and install new lighting.

In spring 2024, construction is anticipated to begin in Robert Brett Park and Belvedere Park. Further details about the design and construction impacts will be shared prior to construction.

Balwin Park and Zoie Gardiner Park are expected to begin construction in spring 2025.

January 2023 - Project Update

This project has received funding for construction and will be moving forward.

November 2022 - What We Heard Report

Thank you to everyone who participated in the engagement for the Balwin and Belvedere Park Revitalization project. A What We Heard report is now available.

September 2022 - Capital Infrastructure Investment Update

Thank you to everyone who attended an event or completed the survey for Balwin and Belvedere Park Revitalization. A What We Heard report will be available in the coming months. This project is currently funded through the planning and design phases. Funding for construction is not currently in place and will depend upon future capital funding.

July 2022 - Capital Infrastructure Investments

Public engagement on the 5 open spaces has concluded and the What We Heard Report is available. Thank you to everyone who participated in the survey and shared ideas on how to improve Balwin and Belvedere Parks.

March 2022 - Capital Infrastructure Investments

Resources to support targeted physical infrastructure improvements in Balwin and Belvedere falls under the Neighbourhood Revitalization Capital Investment Plan. Some examples are enhanced lighting, benches, public art, wayfinding features and park redevelopment. Investments in physical infrastructure enhance public spaces such as roadways, alleys, open spaces, and parks, to increase social connection, beautification, economic vibrancy and safety.

Capital Investments - What We Decided (March 2022)

Contact Us

Curtis Reid

Project Coordinator

Email  openspacedelivery@edmonton.ca