Construction will be starting and will consist of road reconstruction which will include the removal of existing asphalt and road base, installation of a subdrain system, placement of new road base, miscellaneous concrete repairs and asphalt paving.
Ozerna
Construction in Ozerna will tentatively begin the week of May 30, 2022. There was a delay for the start of construction due to a supply issue. The contractor will be sending out another bulletin to all residents to inform them of the start date change.
Ozerna 2022 Scope Map
Mayliewan
Construction in Mayliewan will begin the week of May 9, 2022.
Mayliewan 2022 Scope Map
Construction is anticipated to be completed in October 2022.
Please watch your mailbox for bulletins that provide additional information on access and landscaping impacts.
During street closures, if a garbage or recycling pick-up occurs, the project team will add new bins to the project area, outside of the portion that is closed to traffic. Please place any waste in the new temporary bin located closest to your property. After construction is complete, regular garbage pick-up dates and locations will resume.