Project Update - December 2020
Neighbourhood renewal work is complete for 2020 in Grandview Heights! The 2020 Grandview Heights construction season began in June and was the first year of the 2-year renewal for this neighbourhood.
In June, work began with the relocation and upgrading of drainage structures. In July, August and September, the renewal of concrete structures (including sidewalks and curbs) in the areas planned for 2020 was completed. In September and October, all planned road reconstruction and paving was completed. The planned 2020 project scope including drainage, road and concrete work was successfully completed on time and on budget. This included the placement of all sod and the new shared-use path on 62 Avenue and Grandview Drive. Street lights will be swapped out on pedestals in the coming months.
Neighbourhood renewal work will resume in Grandview Heights in May 2021, exact dates depend on the weather. Prior to work resuming, construction notifications will be delivered to impacted residences.