The Latta Bridge, located along Jasper Avenue, northeast of 91 Street and southwest of 90 Street, will be replaced.

Tree removal will begin mid-February 2022. 
Learn More

 

Project Update - January 2022

  • Tree Removal will begin February 2022
  • The project is currently in the detailed design phase, anticipated to be completed in February 2022
  • A public information session is anticipated for spring of 2022
  • Construction is anticipated to begin in August 2022 

Tree Removals and Protection Plan

aerial view of latta bridge sketch

see larger view

About the Project

Latta Bridge was originally constructed in 1911 and currently serves as an arterial roadway with 4 lanes of traffic. Latta Bridge is located along Jasper Avenue, northeast of 91 Street and southwest of 90 Street.

The bridge crosses Latta Ravine, the site of a maintenance access trail, which provides further access to Dawson Park and the river valley.

A Condition Assessment, Load Evaluation and Management Strategy Report was completed in December 2019 and recommended full replacement of the bridge.