Construction Update - October 2016

All concrete and road work has been completed.  Due to current weather conditions, some landscaping and minor work will be carried out during the 2017 construction season.

Construction Update - October 31, 2016

Project Update - Spring 2016

Construction began on May 2, 2016 and it is expected that the duration of construction in front of your residence may be up to 12 weeks (weather dependent).

The construction consists of removal and replacement of public sidewalk, curb and gutter, streetlight replacement as required and reconstruction and paving of the road.

Construction Bulletin

Project Update - March 2016

On March 30, 2016 the City met with businesses around the High Street area and on April 22, 2016 the City met with businesses adjacent to 124 Street. These meetings were to discuss the upcoming construction and potential impacts to businesses' access and parking as part of Westmount's neighbourhood reconstruction. The following displays were presented at these meetings.

Construction Areas by Year

Construction Project Areas

Proposed Total Closures Adjacent to 124 Street

Proposed Staging Areas at 102A Avenue and 103 Avenue

Project Update - October 27, 2015

Some 2016 work in Westmount was moved ahead and completed in 2015, including 109 Avenue from 128 Street to 129 Street, Woodbend Place and Glenora Pointe.

Westmount - Preliminary Design

Work in Westmount will resume in spring 2016 in the other areas outlined in the project scope map.

Project Update - Spring 2015

Neighbourhood Renewal in Westmount begins the week of May 4, 2015. Please anticipate that the duration of construction may be up to 12 weeks in front of your residences (weather dependent)

Construction Bulletin - April 13, 2015

Meeting Four - February 12, 2015

On Thursday, February 12, 2015, City representatives gave detailed information regarding the design, construction, and local improvement process for the Westmount neighbourhood renewal project. Below are the links to the presentation materials as well as any information that was distributed and displayed.

What We Heard

Meeting Three - November 13, 2014

On Thursday, November 13, 2014, City representatives gave detailed information regarding the design, construction, and local improvement process for the Westmount neighbourhood renewal project. Below are the links to the presentation materials as well as any information that was distributed and displayed.

What We Heard

Meeting Two -  April 9, 2014

On Wednesday, April 9, 2014, City representatives gave detailed information regarding the design, construction, and local improvement process for the Westmount neighbourhood renewal project. Below are the links to the presentation materials as well as any information that was distributed and displayed.

Meeting One – June 18, 2013

The Building Great Neighbourhoods team met with the Westmount Community League Executive to share the City’s plans to renew and replace sanitary and storm sewers, reconstruct roads, curbs and sidewalks on City-owned property, and replace streetlights starting in 2015. The City also explained how Westmount residents and property owners will have the opportunity to get involved in the Complete Streets Pilot Project for the neighbourhood.

Building Great Neighbourhoods/Complete Streets Pilot Presentation

What We Heard

For More Information

Building Great Neighbourhoods

All additional inquiries can be directed to the Building Great Neighbourhoods team, or by calling 311

Email buildinggreatneighbourhoods@edmonton.ca