Main page content begins here

Bridges along Groat Road are undergoing rehabilitation with anticipated completion in fall 2020.

Project Update - December 2019

Equipment transitions, including reassembly of the gantry crane on the east side of the bridge, has been completed. Vehicular traffic was relocated to the new west side of the bridge on Tuesday December 3, followed shortly by a temporary pedestrian route along the centre of the bridge.

The access points for the sidewalk remain the same as before. Large concrete barriers have been installed on the west of the sidewalk to separate pedestrians from traffic, and fencing along the east keeps the sidewalk separated from the new construction site. Due to the narrow width, cyclists must continue to dismount while using the sidewalk or ride along the bridge deck.

Additionally, due to the proximity to the construction site, pedestrians and cyclists who dismount will occasionally be signaled to stop at the discretion of flag persons in order for equipment to move into and out of the new job site on the east side of the bridge.

All users are urged to use caution and to watch for traffic at either end of the bridge deck when accessing the temporary sidewalk. Please refer to the map for further details.

Future Closures

Future closures are expected through the duration of the project and are expected to proceed as follows:

River Valley Road Impacts

Superstructure Demolition- Winter/Spring  2019 & Winter/Spring 2020 

Demolition of the northernmost portion of the existing bridge superstructure will take place over River Valley Road. This demolition work is completed utilizing a large land-based crane to disassemble the end span of the bridge; due to the footprint of the crane and the risk associated with hoisting heavy loads in excess of 100 tonnes, River Valley Road will be closed for the extent of these particular demolition operations.


Girder Installation - Spring/Summer 2019 & Spring/Summer 2020

Following the demolition of the existing bridge superstructure, new steel bridge girders will be installed as the first step in the reconstruction of the bridge. Installing the bridge girders on the northernmost portion of the bridge will require closures of River Valley Road in order to ensure the safety of the traveling public as loads of up to 80 tonnes are hoisted over the road and secured into place.


Bridge Abutment Reconstruction - Winter/Spring 2019 & Winter/Spring 2020

During reconstruction of the north bridge abutment located on the north edge of River Valley Road, it may be necessary to implement short-duration road closures for logistically-restricted construction operations, such as major concrete pours. These restrictions will generally be short duration and limited in nature.

Groat Road Bridge Impacts

Bridge Deck Reconstruction - Spring/Summer 2019 and Spring/Summer 2020

Major concrete pours that are required for reconstruction of the new bridge deck will require full closures of Groat Road Bridge due to spatial constraints and to ensure long-term construction quality. These concrete pours will occur during nighttime hours to minimize impacts to commuters.

About the Project

In 2018, the City began the rehabilitation of 3 Groat Road bridges and Groat Road from 87 Avenue to the North Saskatchewan River. Bridges along Groat Road are undergoing rehabilitation with anticipated completion in fall 2020.

Project Timeline

Construction - Began April 18, 2018

Pre-construction Information Session - March 2018

Tendering Period - November-December 2017

Detailed Design - Completed October 2017

Preliminary Design - Completed November 2016

Field Investigation - As part of the permitting process for this project, the Project Team completed a field investigation in spring 2017 to determine if historical or archeological artifacts are present in the key portions of the project area

Project Details

Groat Road Bridge over the North Saskatchewan River
The Groat Road Bridge over the North Saskatchewan River was constructed in 1955. The last major rehabilitation of this bridge occurred in 1989-1990. Rehabilitation will extend its service life by at least 50 years and improve the functionality of the existing sidewalk by widening it to shared-use path standards.

Groat Road Bridge over Victoria Park Road
The Groat Road Bridge over Victoria Park Road was constructed in 1954. The bridge is generally in good condition but currently requires a wearing surface replacement, new deck joints and other miscellaneous repairs.

Emily Murphy Park Road Bridge over Groat Road (Mayfair Bridge)
The Emily Murphy Park Road over Groat Road bridge was constructed in 1963. The bridge is generally in good condition but requires some minor rehabilitation to extend its service life until more substantial rehabilitation work is needed in 10 years or more. Additionally, the north sidewalk will be widened to shared-use path standards.

Roadwork
Groat Road from 87 Avenue to the Groat Road Bridge over the North Saskatchewan River, including the ramps at Emily Murphy Park Road/Bridge and Hawrelak Park, will be renewed as part of this project. Work is anticipated to be complete by 2020.

The sidewalks on the east side of the ramp from Emily Murphy Park Road and from the Mayfair Bridge to Hawrelak Park will be widened to shared-use path standards.

Phase 1 Demolition Sequence

Project Photos

Stay Informed

Sign up to receive updates on the project and major milestones

Current Traffic Disruptions

Know what's happening and plan your commute.

For More Information

Jim Murray

Telephone

780-944-7667

Email Jim.Murray@edmonton.ca

End of page content. Please choose between the following five options:

Back to main menu Back to current page menu and content View current page breadcrumb Back to site search Continue to page footer content