Parks and Open Spaces
Improvements to John A. Norris Park, Linear Park and Rocketship Park also occurred in 2021. If you have any questions or concerns, please email openspacesdelivery@edmonton.ca.
Main page content begins here
Neighbourhood Renewal in Inglewood was completed in 2021.
Improvements to John A. Norris Park, Linear Park and Rocketship Park also occurred in 2021. If you have any questions or concerns, please email openspacesdelivery@edmonton.ca.
Construction on the Inglewood Park Redevelopment is scheduled to begin in June with completion anticipated in September 2022.
The project will include installation of a spray park with an external water filling station, concrete pads to accommodate new park furnishings and replacement/upgrades to existing park furnishings such as benches and picnic tables.
128 Street and 112 Avenue
Construction of the new community space which includes a new shelter structure and walking path, has been completed. Due to delivery delays, park furniture (picnic tables and benches) will be installed in November 2021 and will not impact opening the park for public use. The final portion of construction will be the installation of additional lighting within the park which will be completed in 2022.
East side of 122 Street between 111 Avenue and 118 Avenue
Construction included improvements to the existing pathway and construction of a new separate dogs off-leash park has been completed. The only work remaining is the completion of the path lighting, which will occur over the winter of 2021/2022.
Construction on the Winnifred Stewart Park project is scheduled to begin in June with completion anticipated in September 2022.
The project will include an addition of a connector walkway to the north east/west corner of the park, a large semicircular area where the new pathway meets the existing sidewalk to the south, a new picnic table with suitable seating and new plantings.
Inglewood has been chosen for reconstruction, beginning in spring 2019, with completion expected for 2021.
Neighbourhood reconstruction is a type of neighbourhood renewal that involves road reconstruction and repaving, as well as replacement of streetlights and reconstruction of sidewalks, curb and gutter. Alley renewal is not part of neighbourhood reconstruction. It also includes the opportunity for two local improvements, sidewalk renewal and decorative streetlights. Inglewood's neighbourhood reconstruction will also include the delivery of the 127 Street corridor concept plan that was developed in 2015 through extensive public engagement.
The What We Decided Report describes the final designs for Inglewood's neighbourhood renewal, including when and how the City used policy and program information, public engagement input and technical requirements to make project decisions.
Ask a question directly to the Inglewood Neighbourhood Renewal project team.
The Inglewood Neighbourhood Renewal has been completed! Construction began in May and was completed in October. During this final year of construction, we completed the following:
With the landscaping portion of the renewal being completed in October 2021, there will be portions of the work that may require some minor repairs come spring 2022.
The final portion of the renewal will be the replacement of lighting in the alley. This is scheduled to begin in the early portion of 2022 throughout the whole of Inglewood.
We are entering the third year of the planned 3-year construction of Inglewood. Construction is progressing on time and on budget. For a breakdown of the planned projects by number in the neighbourhood, see the Project Map.
The 2020 construction season was a success and we completed all planned construction in project areas 13, 14, and the majority of 15. The completed work included roadways, sidewalks, drainage and a portion of the street lighting. The landscaping was only complete up to topsoil, so starting in may of 2021 the landscapers will be onsite to top-dress the topsoil and start installing sod.
Street lighting will continue in all previous project areas as well as start in the remaining project areas of 16 and 17 this summer.
The 2021 construction season will include the removal and replacement of public sidewalks, curbs and gutters, as well as street lighting. Reconstruction and paving of the roads in the project areas of 15 (remainder along 114 Avenue), 16, 17 will also be completed.
Please watch your mailbox for construction bulletins that will provide more information along with detail for any concerns regarding landscaping and access.
We are through the second year of 3-year planned construction for Inglewood. For a breakdown of the planned projects by number in the neighbourhood, please see the Project Map.
The removal and replacement of public sidewalks, curbs and gutters and roadways is complete in projects 10, 11, 12, 13, 14 and 15. Not all the sod in projects 13, 14 and 15 was installed so we will be returning in early spring to finish the landscaping.
The outstanding landscaping from 2019 is complete (projects 10, 11 and 12).
Street lighting in projects 12, 13, 14, and 15 is ongoing and includes running new conduit, drilling new pole bases, then installing new poles and re-energizing the lights. EPCOR is energizing the new poles and completing their quality control checks while removing the old pole bases; this work will continue through 2021.
Neighbourhood renewal work will resume in Inglewood in May 2021, weather pending. Prior to work resuming, construction notifications will be delivered to impacted residences. We are pleased to report that, with the completion of 2020 work, Inglewood remains on schedule with a planned completion date of November 2021.
As part of Inglewood’s neighbourhood renewal, Linear Park will also be renewed starting in 2021. The City is proposing enhancements to improve the usage, beauty and safety of Linear Park. These changes will offer new and different uses of the parks and improve how all users access or travel through the park. During Inglewood neighbourhood renewal, public engagement input was used, along with technical requirements, policy, and program information to identify key functions and design features of Linear Park.
Thank you to everyone who shared their feedback on the Draft Design for Linear Park in our September survey.
We are looking at some enhancements to improve the use, beauty and safety of Linear Park. These changes will offer new and different uses of the parks and improve how all people use or travel through the park. Read the summary of What We Heard from the last time we engaged with you on this project.
We are halfway through the second year of planned 3-year construction for Inglewood. For a breakdown of the planned projects by number in the neighbourhood, see the Project Map.
Construction in 2020 includes the removal and replacement of public sidewalks, curb and gutters, roadways as well as street lighting. The landscaping is working in close proximity to the concrete work this year with hopes to have over 80% of the sod down prior to the end of the summer construction season.
Street lighting in projects 10 and 11 are now complete. EPCOR is now working in projects 12, 13, 14 and 15, which includes running new conduit, drilling new pole bases, then installing new poles and re-energizing the lights. The decorative poles started to come into stock over the winter so EPCOR will be replacing the old poles. As they go along and energize the new poles and complete their quality control checks, they will be removing the old pole bases.
We are entering the second year of planned 3-year construction for Inglewood. For a breakdown of the planned projects by number in the neighbourhood, see the Project Map.
The 2019 construction season was a success and we completed all planned construction in project 10, 11 and 12 which included the roadways, sidewalks, drainage and a portion of the street lighting. The landscaping was only complete up to topsoil so in June and July, the landscapers will be onsite to top dress the topsoil and start installing sod.
Street lighting will continue in projects 10, 11, 12, 13, 14 and 15 this summer. The decorative poles started to come into stock over the winter so EPCOR will be replacing the old poles.
The 2020 construction season will include the removal and replacement of public sidewalks, curbs and gutters, as well as street lighting. Reconstruction and paving of the roads in projects 13, 14 and 15 will also be completed.
Please watch your mailbox for construction bulletins that will provide more information along with contact details for any concerns regarding landscaping and access.
The first year of construction for Inglewood's neighbourhood renewal is almost complete! Here's what's been completed so far and what is still to come in 2019:
All sidewalk reconstruction east of 124 Street is almost complete. Work will continue on the remaining connectors and driveway pours this month as well as 2 raised crosswalks on 122 Street and a curb extension south of 118 Avenue.
Road work east of 124 Street will begin this month and all paving will be complete east of 124 Street for mid-October.
Sidewalk, curb and gutter removals have started west of 124 Street.
Street lighting upgrades have started with new bases and galvanized poles being installed; decorative street lights will be installed in 2020.
Want to know more about the early planning and design process for Inglewood? The Urban Design Analysis describes the creative ideas, policy, and technical inputs considered to help inform the final design for neighbourhood renewal.
The UDA is a snapshot in time where we explored opportunities for the neighbourhood. This analysis was undertaken in 2018 and the report was published in 2019. Since this time, new projects may have started which are not captured in the background information provided in the UDA.
Construction for Inglewood's Neighbourhood Renewal is underway. Over the first month, crews started work on the east side of the neighbourhood, working along 122 Street and 123 Street.
Sidewalk reconstruction is ongoing on the west side of 123 Street and all catch basins on the street have also been upgraded. Sidewalk reconstruction along 122 Street began this week and upgrades to catch basins on the street will begin in July.
Thank you to all residents and Inglewood visitors for your patience during construction. If you have any questions or concerns regarding your property, please contact the Delivery Project Manager so we can address your questions as soon as possible. We look forward to continuing to work together and making the most out of your neighbourhood!
Construction is now underway in Inglewood. The construction consists of removal and replacement of public sidewalk, curb and gutter, and street lighting, as well as reconstruction and paving of the road.
The Spring Bulletin contains important project and contact information for residents and property owners. The Prime Contractor working for the City will deliver bulletins outlining the estimated start/finish dates of each portion of the project, along with their contact information.
Thank you to those who attended the Inglewood Neighbourhood Renewal pre-construction event on Saturday April 27, 2019 to view the final designs for your neighbourhood and learn more about what to expect during the planned 3-year construction.
The final neighbourhood designs were developed based on the feedback received throughout the public engagement process, and also considered City policies, programs, and technical considerations. The final neighbourhood designs include:
Attendees also had the opportunity to speak to project team members for Inglewood's Neighbourhood Revitalization and 124 Street (111 to 118 Avenue) Renewal.
Meeting Materials
Construction Boards
Display Boards
What We Decided Report
Thank you to everyone who dropped by the Inglewood Neighbourhood Renewal Preliminary Design Event to share your input on the preliminary designs for new and renewed infrastructure in the community. If you were not able to attend, please see the event materials.
At this event, property owners had the opportunity to learn and make a decision about the sidewalk and decorative street light Local Improvements. Inglewood Revitalization and 124 Street Renewal (111 to 118 Avenue) project teams were also in attendance.
Event Materials
What We Heard (October 2018)
Project Background and Preliminary Designs
Local Improvements
Thank you to everyone who joined us on Tuesday October 2, 2018 to view and provide feedback on the draft concepts for Inglewood Neighbourhood Renewal, including:
The following months will be used to fine-tune the design based on public feedback and to fully develop the technical and other elements of the plans. The preliminary design will be shared with the community in early 2019, prior to construction in spring 2019.
On August 16, 2018, the City hosted an event to seek input on concepts for the Inglewood neighbourhood. Attendees were asked to:
Traffic Calming Measures
The City installed temporary examples of traffic-calming measures in the Inglewood neighbourhood two days before the event at the following locations:
Each location features a different traffic-calming measure that could help address speeding and shortcutting in your neighbourhood. They will help residents to get an idea of what they look and feel like and how they impact travel in your neighbourhood. These will be in place for about two weeks and you can provide feedback for each measure through the survey boards located near each location. Your input on these example measures will help inform decisions on types and locations for final traffic-calming measures in Inglewood. Concepts will be shared to the public in the fall for further feedback.
Meeting Materials
Display Boards
Renewal and Revitalization
What We Heard
In April 2018, Building Great Neighbourhoods held 2 workshops. The goals were to have attendees assist in refining a project vision and important elements, and to provide their feedback on what the City should consider as we renew the infrastructure in Inglewood.
Meeting Materials
Display Boards
Aerial View
Factsheet
Representatives from community groups and organizations in Inglewood were invited to a stakeholder outreach workshop to learn more about the Inglewood neighbourhood renewal and to have a conversation about building outreach capacity for later public engagement on the project.
The workshop was also used to gather initial ideas for what the community, as a whole, is hoping the renewal work will achieve. Themes from the input gathered in the workshop will be presented in future engagement opportunities for the public to review and refine.
Presentation
Fact Sheet
Title | Delivery Project Manager |
---|---|
courtney.beamish@edmonton.ca |
All additional inquiries or escalations can be directed to the Building Great Neighbourhoods team by calling 780-496-4055 or by calling 311.
BuildingGreatNeighbourhoods@edmonton.ca |