Find information on the public engagement history for the Pleasantview Community Traffic Management Plan.

The Community Traffic Management process in Pleasantview is complete.

In the fall of 2013 residents, businesses and other stakeholders in Pleasantview expressed concerns about traffic issues including speeding, traffic volumes and shortcutting.

In January 2014 The City began organizing opportunities for residents of Pleasantview and surrounding communities to share concerns and identify traffic challenges.

Engagement Process and Reporting Back

Community Meeting

February 3, 2016

A community-wide meeting was held to review what we heard from previous meetings as well as the community survey, and to report back about next steps for the trial traffic measures.

Fact Sheet
FAQ Sheet
Phone Survey Report 2016
Presentation
Public Engagement Summary Report
What We Heard Report - October to November 2015
What We Heard Summary - February 2016

2015

Public Workshop

November 26

The City held a public workshop to share the project information and to gain feedback from citizens on the trial traffic measures in Pleasantview.

Traffic Data Map
November 26, 2015 - Presentation
November 26, 2015 - Meeting Transcript

 

Area Meetings

Meetings were held to share information and gather feedback about the progress to date and what next steps would be.

106 Street Area Meeting

November 19, 2015 - Meeting Transcript

109 Street Area Meeting

October 29, 2015 - Meeting Transcript

Information Session

April 30

The Traffic Committee presented a trial traffic management plan to respond to concerns about high traffic volumes, speeding and shortcutting in the Pleasantview community.

What We Heard
FAQ
Detailed Map
Display Boards
Factsheet
Presentation
Centre Median Illustration
Curb Extension Illustration
Intersection Modificiation Illustration
One-Way Illustration

2014

Public Drop-In Workshops

March 11 and 19

Discussion topics where around traffic measures that were supported, suggestions for a school drop-off area, issues not in scope of this initiative and suggestions for installations and enforcement to calm traffic.

318 people attended the workshops:

  • 147 on March 11
  • 171 on March 19

Pleasantview Workshop Feedback
Factsheet
Project Boards
Maps
Traffic Measures Handout

Traffic Management Plan Survey

January 13 to 26

Residents were asked to complete a preliminary survey to assess community concerns, including perceptions of:

  • Traffic volume and safety;
  • Locations and types of traffic issues; and
  • Willingness to accept traffic measures that may increase travel time.

The survey was open to anyone in Edmonton.
201 respondents completed the survey.


Pleasantview Survey Report

For More Information

311 Contact Centre

Online Contact 311 Online
Telephone

In Edmonton: 311
Outside Edmonton: 780-442-5311

TTY 780-944-5555
Email 311@edmonton.ca

End of page content. Please choose between the following five options:

Back to main menu Back to current page menu and content View current page breadcrumb Back to site search Continue to page footer content