About the Project

Neighbourhood renewal in Capilano was successfully completed in 2013.

  • Neighbourhood reconstruction began in summer 2011.
  • The City worked on 27 project areas between 2011 and 2013.
  • Construction included roadway reclamation, streetlight upgrades and reconstruction of the sidewalk, curb and gutter.
  • The cost-share portion of sidewalk reconstruction paid by property owners was a lump sum of $154.17/m or $12.12/m per year for 20 years.

Funding

Neighbourhood renewal projects are paid for by property taxes, provincial funding and cost sharing. The City and property owners will share the cost of sidewalk reconstruction through a 50/50 Local Improvement tax levy. This levy can be paid in one lump sum, or over a period of 20 years.

Project History

February 2, 2011 - Public Open House

The project team provided information and answered questions about neighbourhood renewal construction in Capilano.

Information for Capilano Residents

Presentations

Overview

Local Improvement Process

Construction Process

For More Information

Building Great Neighbourhoods

All additional inquiries can be directed to the Building Great Neighbourhoods team, or by calling 311

Email buildinggreatneighbourhoods@edmonton.ca

End of page content. Please choose between the following five options:

Back to main menu Back to current page menu and content View current page breadcrumb Back to site search Continue to page footer content