Project Update

This application was refused by City Council at a Public Hearing on June 28, 2017. Consult the June 28, 2017 Council Minutes (Item 5.1) for details.

Public Open House

A Public Open House was held on April 6, 2017. Thirty-one citizens attended this meeting at the Oliver School.

Project Timeline

Pre-Consultation Discussions

September 23, 2016 - Applicant sent out pre-application notices to surrounding property owners and the Oliver Community League to seek initial feedback on the application.

September 12, 2016 - Applicant had pre-consultation meeting with Oliver Community League Civics Committee.

City Processing

January 11, 2017 - City sent notices to surrounding property owners and the Oliver Community League.

December 5, 2016 - City circulated application to City departments and utility agencies for technical review.

November 21, 2016 - The City of Edmonton accepted this application.

For More Information

Andrew McLellan

Title Planner
Telephone

780-496-2939

Email andrew.mclellan@edmonton.ca