July 29, 2011 - Project Moving Into Preliminary Design Phase

The Walterdale Bridge Replacement project is moving into the preliminary design phase and will be implemented on behalf of The City of Edmonton by ISL Engineering and Land Services Ltd.

Walterdale Bridge Replacement Project - July 2011 Update

April 27, 2011 - Walterdale Bridge Replacement Concept Plan Approved by City Council

City Council Minutes

Public Involvement Report

Throughout the concept planning phase for the Walterdale Bridge Replacement, public involvement played an important role in the analysis and selection of the preferred option, recognizing that the new bridge will become a point of pride for the citizens of Edmonton and a gateway to Edmonton’s downtown.

The public involvement plan was developed as a three-phase approach to be undertaken throughout the concept planning process. The information gathered throughout the public involvement process was used to seek local knowledge about potential benefits and impacts of the various road and bridge options, and to identify items for further study and consultation as development of the recommendation proceeds into future design phases.

Walterdale Bridge Public Involvement Report

April 12, 2011 - Walterdale Bridge Replacement Concept Plan Presentation

Presented to Transportation and Public Works Committee on April 12, 2011.

The Walterdale Bridge Replacement Concept Plan

Transportation and Public Works Committee Agendas

March 22, 2011 - Walterdale Bridge Information Session

The project team shared information on the recommended alignment, bridge-style, and associated roadway improvements.

Documents

Walterdale Bridge Visual Concepts

Walterdale Bridge Project Background

Bridge Alignment and Style Recommendation Fact Sheet

Information Session Presentation

Questionnaire

January 25, 2011 - City Council Direction

A project status report was presented to the Transportation and Public Works Committee. The report included a summary of the bridge replacement options and styles under review.

Following the direction from the meeting, construction scheduled for 2013-14 will include bridge replacement and minor roadwork to connect the bridge to the existing roadways. Major changes to the north and south approach roads will not be pursued.

Transportation and Public Works Committee Minutes (January 25, 2011)

November 18, 2010 - Open House

The City presented information and obtain public input related to bridge and road alignment options and bridge styles under consideration by the project team.

Documents

Comment Form

Open House Presentation

Walterdale Bridge Alignment Options

Walterdale Bridge Style Options

Walterdale Bridge Condition Assessment (2000)

The Walterdale Bridge Condition Assessment was completed in 2000. The study detailed the bridge’s condition in 2000, evaluated the life expectancy of its components, and planned a rehabilitation plan to extend existing life by 10 years. In 2004, extensive rehabilitation was completed to extend the bridge to 2014.

Walterdale Bridge Rehabilitation Assessment Summary

For More Information

Robin Casavant

Telephone 780-944-7677
Email robin.casavant@edmonton.ca

End of page content. Please choose between the following five options:

Back to main menu Back to current page menu and content View current page breadcrumb Back to site search Continue to page footer content