Rehabilitation will occur in the eastbound direction of Whitemud Drive. The 5.1km stretch runs from the west side of Rainbow Valley bridge to the east side of the 97 Street underpass. It is a 6 lane divided freeway with a posted speed of 80 km/hr.

The scope of work includes:

  • Mill and overlay with crack repairs
  • Selective replacement of curb and gutter
  • Replacement of underpass concrete slabs at 97 Street
  • Guardrail removal and installation
  • Streetlight replacement west of 122 Street
  • Drainage facility repairs and replacements

Project Timeline

Construction is scheduled to begin in June 2019 and expected to be complete in October 2019.