Construction on these bridges and staircases in the Mill Creek Ravine started in early 2021.

Project Update - March 2021

Work began in March 2021 and will be substantially completed by fall 2021 with any final cleanup and miscellaneous incomplete work to be completed in the spring of 2022 (if required).

This work will require closures of the trails located in the Mill Creek Ravine area, with detours in place, in order to accommodate bridge and staircase replacements.

Construction Impacts

The work is scheduled to occur in 3 groups in order to limit the impact of trail closures so that access in the area can be maintained. Work on Group 1 started in March 2021.

About the Project

Eleven pedestrian bridges and 4 staircases located in Mill Creek Ravine, east of 50 Street and north of 34 Avenue, are past the point of maintenance and are needing to be replaced.

These trails, pedestrian bridges and staircases are important connections. The Mill Creek Ravine in this area is a busy recreational spot that is used by people walking, biking, jogging, dog-walking, cross-country skiing and bird watching.

Trail Closure Maps

Trail, bridge and staircases will be divided into 3 groups for construction.

This map indicates the first phase of construction.

This map indicates the second phase of construction.

This map indicates the third phase of construction

Project Timeline

build phase

2021

Phased construction begins

2020

Fall/Winter

  • Design finalized
  • Construction contract tendered and awarded

For More Information

Ryan Drummond

Telephone

780-496-1105

Email Ryan.Drummond@edmonton.ca