Once the design has been completed and approved for construction, the project then moves into the Build Phase. The projects in this section will be either awaiting the start of construction or construction is underway. Although the construction is carried out by the Developer, the City takes an active role in monitoring the work being completed to ensure that it adheres to the previously approved design plan and the City of Edmonton Design and Construction specifications.

25 Avenue

25 Avenue SW: 66 Street to Savaryn Drive

Detailed Design Approved for Construction

The extent of this project to construct the first two lanes of 25 Avenue SW. Construction is anticipated to start in 2017.

Developer Consultant

Brookfield Residential

Stantec Consulting Ltd.

25 Avenue SW: Watt Drive to 66 Street

Detailed Design Approved for Construction

The extent of this project to construct the first two lanes of 25 Avenue SW. Construction is anticipated to start in 2017.

Developer Consultant

Melcor Developments Ltd.

IBI Group Inc.

28 Avenue

28 Avenue SW: Chappelle Boulevard to Future West Collector

Detailed Design Approved for Construction

The extent of this project is to construct first two lanes of 28 Avenue SW from Chappelle Boulevard to a future collector road further west.

This project is anticipated to start in the 2017 construction season.

Developer Consultant

Brookfield Residential

Stantec Consulting Ltd.

41 Avenue

41 Avenue SW: Heritage Valley Trail to Chappelle Road

Detailed Design Approved for Construction

The extent of this project is to construct the first two lanes of 41 Avenue SW from Heritage Valley Trail to Chappelle Road in order to accommodate growth and increased traffic flows from future developments. This project is carrying over from 2016 and will be completed in the 2017 construction season.

Developer Consultant

Delcon Creekwood Master GP Ltd./Sherrick Management

Al-Terra Engineering Ltd.

41 Avenue SW: James Mowatt Trail to Desrochers Drive

Detailed Design Approved for Construction

The extent of this project is to construct two urban lanes and remove the existing lanes. The road will be fully closed to traffic from April 17, 2017 until October 31, 2017. Access for local residents will be maintained.

Developer Consultant

MLC Group
Dave Iwaskow, Construction Manager
780-401-2247

Stantec Consulting Ltd.
Tariq Mahmood, Principal
780-917-1899
Scott Gilroy, Site Engineer
780-995-2997

41 Avenue SW: Desrochers Drive to Heritage Valley Trail

Detailed Design Approved for Construction

The extent of this project is to construct two urban lanes and remove the existing lanes. The road will be fully closed to traffic from April 17, 2017 until October 31, 2017. Access for local residents will be maintained.

Developer Consultant

Delcon Creekwood Master GP Ltd./Sherrick Management

Al-Terra Engineering Ltd.
Brad Crossland, Project Engineer
780-440-4411

50 Street

50 Street: 14 Avenue SW to 25 Avenue SW

Detailed Design Approved for Construction

The extent of this project is to construct the first of two urban lanes. This project is carrying over from 2016.

Developer Consultant

United Communities

Stantec Consulting Ltd.

66 Street

66 Street: 25 Avenue SW to Winspear Common (Shaw Way)

Detailed Design Approved for Construction

The extent of this project is to construct the first two lanes. This project is anticipated to start in 2017.

Developer Consultant

Melcor Developments Ltd.

IBI Group Inc.

66 Street: South of 178A Avenue to Transportation Utility Corridor (TUC)

Detailed Design Review Process

The extent of this project is to construct right and left turn bays along 66 Street at the intersection with future 178 Avenue (Crystallina Nera).

Developer Consultant

Maclab Enterprises
Bill Blais
780-420-4058
Email

Stantec Consulting Ltd.
Paul Biagi
780-969-6592
Email

92 Avenue

92 Avenue: 215 Street to 231 Street

Detailed Design Review Process

The extent of this project is to construct the ultimate roadway from 215 Street to 231 Street including roundabouts at each intersection. This project is anticipated to start in 2017 with some staging required.

Developer Consultant

MLC Group

Al-Terra Engineering Ltd.

127 Street (Goodridge Blvd)

127 Street (Goodridge Blvd.): Transportation Utility Corridor (TUC) to Goodridge Collector

Detailed Design Approved for Construction

The extent of this project is to construct the ultimate roadway from Goodridge Collector to the TUC. This project is anticipated to start in 2017.

Developer Consultant

City of Edmonton

Al-Terra Engineering Ltd.

199 Street

199 Street: 23 Avenue NW to 35 Avenue NW

Detailed Design Approved for Construction

The extent of this project is to construct the ultimate roadway from 23 Avenue NW to 35 Avenue NW. This project started in 2016 and will carry on into the 2017 construction season.

Developer Consultant

Qualico Communities

Stantec Consulting Ltd.

199 Street: 23 Avenue NW to 17 Avenue NW

Detailed Design Review Process

The extent of this road construction is to construct the first 2 lanes of 199 Street from 23 Avenue NW to 17 Avenue NW.

Developer Consultant

Mattamy Homes

Scheffer Andrew Ltd.

231 Street

231 Street: Stony Plain Road to South of 97 Avenue

Detailed Design Approved for Construction

The extent of this road construction is to construct the first 2 lanes of 231 Street from Stony Plain Road to the Secord neighbourhood collector road to accommodate growth and increased traffic flows from future subdivision developments.

This project is anticipated to be completed in the 2017 Construction Season.

Developer Consultant

Walton International Group

Stantec Consulting Ltd.

Heritage Valley Trail

Heritage Valley Trail: 41 Avenue SW to 141 Street Collector

Detailed Design Approved for Construction

The extent of this project is to construct the first 2 lanes of Heritage Valley Trail from 41 Avenue SW to the 141 Street collector road to accommodate growth and increased traffic flows from future subdivision developments. This project is starting in the 2017 construction season.

Developer Consultant

Delcon Creekwood Master GP Ltd./Sherrick Management

IBI Group Inc.

Hiller Road

Hiller Road: 170 Street to 178 Street

Detailed Design Approved for Construction

The extent of this project is to construct third and fourth lanes of Hiller Road from 170 Street to 178 Street in order to accommodate the growth and increased traffic flows from future developments. This project is anticipated to be completed in the 2017 construction season.

Developer Consultant

Beaverbrook Developments Inc.

IBI Group Inc.

Hiller Road: 178 Street to 182 Street

Detailed Design Review Process

Construction of first 2 lanes. This project is anticipated to start in 2017.

Developer Consultant

MLC Group

IBI Group Inc.

Parsons Road

Parsons Road: South of Ellwood Drive

Detailed Design Approved for Construction

A right turn bay will be added to the south side of Ellwood Drive.

Developer Consultant

Cameron Development Corp.

Invistec Consulting Ltd.

Riverview Blvd

Riverview Blvd.: Old 23 Avenue to Future 23 Avenue

Detailed Design Review Process

Construction of first 2 lanes. This project is anticipated to start in 2017.

Developer Consultant

Qualico Communities

MMM Group

For More Information

Subdivision & Development Coordination