Project Update - November 2014

The Manning Drive recommended concept plan is now available for review.

Manning Drive Recommended Concept Plan

Highlights of the plan include:

  • Roadway increased from 4-lanes to 6-lanes
  • New west-side sidewalk from 142 Avenue to 144 Avenue
  • New sidewalk connections for existing sidewalks
  • New signal at 160 Avenue with turning lights
  • Improved southbound to westbound turning lane at 137 Avenue

Project Update - August 2014

The Manning Drive draft concept plan is now available for review.

Manning Drive Draft Concept Plan

If you would like to provide feedback on the draft concept plan please contact the project team.

For More Information

Joleen Mazurat

Title Senior Engineer
Telephone

780-944-7659

Email joleen.mazurat@edmonton.ca