Project Update - September 2014

  • On September 15, 2014, the south side of 63 Ave from 99 Street to 104 Street reopened to traffic.
  • There will be single-lane closures in early October for landscaping, guardrail construction and site cleanup.

Project Update - August 2014

  • Base asphalt is 90% complete.
  • Concrete has been completed except for some minor tie-in work.
  • The south retaining wall is completed.

Upcoming:

  • Final asphalt work from 99 Street to 104 Street.
  • Retaining wall backfill, structural walk and railings will be constructed on the south side of 63 Avenue.
  • Work will begin on crash protection and guardrails.

Construction Update - July 2014

  • Work has been completed on concrete pours for new south retaining wall on railway overpass.
  • Grading and gravel underway from 99 Street to 100 Street and from 103 Street to 104 Street.

Construction Update - November 2013

Pavement markings and the last paving of the intersection at 99 Street was completed in early November followed by the opening of the westbound lanes. The work required along Allendale Road has been deferred until 2014.

Construction Update - September 2013

  • Traffic detoured on 63 Avenue with one lane eastbound and two lanes westbound.
  • Construction on Calgary Trail/104 Street complete except for minor concrete work.
  • Construction on 63 Avenue continues.
  • Allendale Road construction may be carried over to 2014 as part of two-year construction schedule.
Traffic Notification - July 14, 2013

Construction Update - August 2013

  • Temporary asphalt walkways completed as part of stage 1 pedestrian accommodation.
  • Traffic detoured on 63 Avenue with one lane eastbound and two lanes westbound.
  • ATCO Gas working on relocations from 99 Street to 100 Street.
  • EPCOR Water relocations complete except for Calgary Trail.
  • Streetlight relocations have begun.
  • Roadway removal underway on 63 Avenue, Allendale Road.
  • Construction on Calgary Trail/104 Street delayed until mid-August due to utility relocations.

For More Information

Alan Herbert

Title Construction Project Manager
Telephone 780-944-7704
Email alan.herbert@edmonton.ca

End of page content. Please choose between the following five options:

Back to main menu Back to current page menu and content View current page breadcrumb Back to site search Continue to page footer content