Project Update - May 2015

Beginning on Friday, May 8, there will be various lane closures on 38 Avenue between 34 Street and 21 Street for road rehabilitation. This work is expected to continue until early August 2015.

Project Update - December 2014

The new section of 38 Avenue was completed in 2014 and is open to traffic. In 2015, we will begin the rehabilitation of the westbound lanes of 38 Avenue and the milling and overlay of the 34 Street and 38 Avenue intersection.

Project Update - September 2014

34 Street & 23 Avenue

  • Streetlights have been installed on 23 Avenue.
  • The 23 Avenue concrete base was completed west of 34 Street.
  • The new NE corner of 34 Street and 23 Avenue was finished.
  • A perched manhole on 23 Avenue and 38 St was completed.
  • Crews have finished work on the centre of the new 34 Street southbound.

38 Avenue (21 Street-34 Street)

  • Granular base has been completed for the roadway widening, as well as most curb and gutter.
  • The asphalt trail has been paved.
  • Streetlights and signals have been installed.
  • Concrete work has been completed and paving is ongoing in the widened roadway.

Project Update - August 2014

34 Street & 23 Avenue

  • In July streetlight installation was completed along 34 Street and nearly completed along 23 Avenue.
  • A concrete base on 23 Avenue was completed west of 38 Street.
  • The shared-use paths on 34 Street and 23 Avenue were completed.

Upcoming:

  • Crews are working to complete the streetlights on 23 Avenue and a traffic signal at 38 Street.
  • Work is anticipated to be finished on the new 34 Street southbound and on 23 Avenue west of 34 Street.

38 Avenue (21 St—34 St)

  • Crews have completed road base preparation and have begun surface construction.

Project Update - July 2014

23 Avenue / 34 Street

  • Streetlights installed on 34 Street and 23 Avenue. Gravel base has been placed on 23 Avenue west of 38 Street
  • Signals completed at 23 Avenue and 38 Street
  • New southbound roadway completed on 34 Street

38 Avenue (21 Street - 34 Street)

  • Drainage work is substantially completed.
  • Final grading of subgrade is ongoing.

Open House - March 2014

On Tuesday, March 25, the City hosted an information session for the widening of 34 Street, 23 Avenue and 38 Avenue arterial roadways. The meeting was an opportunity for the City to share the final roadway designs and the construction schedule for 2014.

August 2012

Concept plans for 34 Street, 23 Avenue, and 38 Avenue were completed in August 2012. The projects will now move into the preliminary design stage.

The roadways will be widened from 2 to 4 lanes, including intersection improvements, landscaping, street lighting and the completion of missing sidewalks and shared-use paths.

Concept Plans

34 Street - 23 Avenue to 34 Avenue

23 Avenue - Mill Woods Road East to 34 Street

38 Avenue - 21 Street to 34 Street

Public Information Session - June 14, 2012

An information session was held at the Southwood Community Hall (1880 - 37 Street). Attendees had the opportunity to learn more about the projects and provided feedback.

Arterial Roadway Widening - Concept Planning Study
Text Displays

Information Session Feedback Summary

34 Street from 23 Avenue to 34 Avenue

23 Avenue from Mill Woods Road East to 34 Street

38 Avenue from 21 Street to 34 Street

For More Information

Gordon Mitchell

34 Street and 23 Avenue

Telephone

780-944-5662

Email Gordon.Mitchell@edmonton.ca

Wayne Squires

38 Avenue

Telephone

780-423-5544