About the Project

Two sections of 111 Avenue will undergo reconstruction in 2018. Travel through the areas will be impacted by the construction, however, attempts will be made to minimize delays.

The scope of each project includes:

124 Street to 132 Street

  • Installation of new pedestrian signals and street lights
  • Minor utility relocation
  • Removal and replacement of concrete curb and gutter, sidewalk and curb ramps
  • Isolated road base repairs
  • Asphalt milling and resurfacing
  • Minor landscaping

142 Street to 149 Street

Construction is scheduled to commence July 23, 2018 and be completed by the fall of 2018.

Scope of work:

  • Removal and replacement of:
    • Drainage infrastructure
    • Sidewalk
    • Curb and gutter
  • Milling and overlay of asphalt surfaces

As part of this work, there will be some alignment changes to the southeast corners of the 142 Street and 149 Street intersections.

Construction Bulletin

Project Timeline

Construction is scheduled to begin in summer 2018 and be complete by fall 2018.

For More Information

Andre Samoil

Telephone

780-944-7698

Email andre.samoil@edmonton.ca