Construction equipment working on Terwillegar Park Footbridge

Final bridge profile from the berm

Project life cycle chevron stating currently in "build" phase

Project Timeline

  • Concept design—July 2013
  • Preliminary design completion—December 2013
  • Construction start—August 2014
  • Construction completion—October 2016
  • Landscaping and art installation—spring/summer 2017

Construction Updates

May 2017

The bridge contractor will be completing landscape deficiency work around the bridge and installing pedestals for the project art pieces this spring. The art pieces are anticipated to be installed this summer. 

Terwillegar Footbridge Construction Photos

For More Information

Tariq Aziz, P.Eng.

Telephone

780-496-8192

Email tariq.aziz@edmonton.ca