Borden Park has served Edmonton's families for 100 years. We are working on a revitalization plan that will see Borden Park's legacy continue for many years to come.

The revitalization plan began in 2010 and over the last four years, major upgrades to the park have been completed. The last remaining piece of the revitalization plan will see the redevelopment of the Borden Outdoor Pool into the Borden Natural Swimming Experience.

Project Timeline

Project Timeline - Build Phase

Summer 2018
Opening to public

Fall 2017
Construction complete and Borden Park Natural Swimming Pool facility turned over to the City for testing.

Spring 2016 - Summer 2017
Construction

Spring 2016
Public Information Session
Renderings

Summer 2014
Borden Park Outdoor Pool closed permanently.

Spring 2012 - Winter 2014
Design Development

Fall 2013
Community and stakeholders provided input through public open house.

Winter 2014
Borden Natural Swimming Experience design was finalized.

Fall 2010
Feasibility study confirms the viability of the Natural Swimming Pond at Borden Park. Project was approved and funded as part of the 2012 Capital Budget Process.

Project Overview

Through the Outdoor Aquatic Strategy 2008-2017, approved by City Council in 2007, Borden Outdoor Pool was designated for rehabilitation. During public consultation and the development of Borden Park master plan, it was determined that a natural swim experience was a great way to maintain the legacy of this historic park.

After getting public input on the facility design in 2013, the project was tendered for construction in June 2014. All bids came in significantly over budget and the City cancelled the tender. In order to stay within budget, the facility was redesigned to find savings and efficiencies. Key program elements including the natural filtration system were kept, while reductions included winter skating opportunities.

Following an extensive re-design, the project was successfully re-tendered at the end of 2015 and construction began in the spring of 2016.

The Borden Natural Swim Experience will be the first public amenity of its kind in Canada and will provide a unique recreational opportunity to Edmontonians.

For More Information

Facility Planning and Design

12th Floor, Edmonton Tower
10111-104 Avenue NW Edmonton
T5J 0J4

Telephone

In Edmonton: 311

Outside Edmonton: 780-442-5311

Email FacilityPlanningAndDesign@edmonton.ca