Main page content begins here

On Saturday, April 28 and Sunday, April 29, buses replace LRT service all day at Clareview, Belvedere, Coliseum and Stadium stations due to planned maintenance work. The Metro Line and all trains at the other stations south of Stadium run every 15 minutes as scheduled.

Replacement buses

  • Run every 7-8 minutes
    On Sunday, buses run every 15 minutes in the early morning before 5:30am and late night after 12:35am
  • Use bus stops with red signs marked “LRT Replacement”
  • Mimic the LRT system, stopping only at or near LRT stations
  • Display “LRT Replacement Service” followed by the final destination.
  • Travel further south to Corona station to accommodate transit users travelling to Downtown

LRT arrival signs will be turned off, but schedule information for LRT trains and LRT replacement buses are available through 311, on the Transit Trip Planner, and third-party apps. Updated schedule information is not available on the ETS Live® Bus Finder).

Regular service is scheduled to resume at the start of service on Monday, April 30.  

Did you know the Capital Line LRT system is 40 years old? A partial LRT closure helps crews safely complete as much planned maintenance as possible to keep the system running smoothly.

Planned work includes:

Clareview station

  • Roof maintenance
  • Electrical maintenance
  • Window repair
  • Flooring repair
  • Platform repair
  • Sidewalk repair
  • Switch replacements
  • Rail replacement

Belvedere station

  • Power pole replacement
  • Electrical maintenance
  • Switch maintenance

Belvedere - Coliseum station

  • Wire replacement
  • Switch maintenance
  • Coliseum window repair

Stadium

  • Wall repair
  • Switch maintenance
  • Electrical maintenance