This program works in mature neighbourhoods to reconstruct or maintain:

  • Streets
  • Sidewalks, curbs, gutters
  • Street lighting
  • Collector roads

The type of work depends on the condition of infrastructure and coordination with other projects in a neighbourhood. The three types of work are:

  1. Reconstruction (roads, sidewalks, curbs, and streetlights are replaced)
  2. Overlay (roads are repaved and sidewalk trip hazards removed)
  3. Microsurfacing (roads are resealed with thin asphalt layer)

Reconstruction and overlay are funded in the capital program and microsurfacing is an operating budget service. The capital program is supported by a dedicated tax in the operating budget and contributions from the Alberta Government. The proposed 2012-14 Capital Budget is based on a 1.5% tax increase per year in the operating budget dedicated to this program.

Key Accomplishments 2009-2011

Since 2009, the City has delivered transportation renewal work in over 20 neighbourhoods each year. Reconstruction projects take 2-3 years to complete while overlays are often completed in one year.

Neighbourhood Reconstruction:

Parkdale (completed 2009)
Lendrum Place (completed 2010)
Meadowlark Park (completed 2010)
Parkallen (started 2010)
Capilano (started 2011)
Fulton Place (to be completed 2011)
Rio Terrace (to be completed 2011)
Sherbrooke (to be completed 2011)
West Jasper Place (started 2011)

Neighbourhood Overlay:

2009
• Delwood • Sakaw

2010
• Balwin • Cloverdale • Daly Grove • Lymburn • Macleod • Ogilvie Ridge • Patricia Heights • Stone Industrial • Summerlea • Westridge

2011
• Bearspaw • Belvedere • Callingwood North • Casselman • Crawford Plains • Duggan • Greenview • Hagmann Estate • High Park Industrial • Kameyosek • McIntyre Industrial • Menisa • Richfield • Weir Industrial

In addition, 96 km of collector roadways were renewed in 2009-2011.

Planned Projects 2012-2014

Reconstruction of neighbourhoods continue over 2 to 3 years, while overlays and microsurfacing in neighbourhoods are usually completed in one year.

Planned Reconstruction:

Argyll (to be completed 2014)
Canora (to be completed 2013)
Capilano (to be completed 2012)
Cromdale (start 2014)
Delton (to be completed 2014)
Dovercourt (to be completed 2014)
Glenora (start in 2014)
Grovenor (start in 2014)
Hazeldean (start in 2014)
King Edward Park (to be completed 2014)
North Glenora (to be completed 2014)
Parkallen (to be completed 2012)
Terrace Heights (to be completed 2014)
West Jasper Place (to be completed 2012)
Windsor Park (to be completed 2013)
Woodcroft (to be completed 2013)

Planned Neighbourhood Overlays:

Alberta Park Industrial (2012)
Aldergrove (2013)
Bannerman (2013)
Belmead (2013)
Bisset (2012)
Brander Gardens (2013)
Dechene (2014)
Ekota (2012)
Kennedale Industrial (2012)
Lago Lindo (2013)
McArthur Industrial (2012)
McNamara Industrial (2012)
Newton (2014)
Ormsby Place - east of 187A Street (2014)
Pollard Meadows (2013)
Ramsey Heights (2014)
Sweet Grass (2014)
Wilson Industrial (2012)

In addition, 53 km of collector roadways, with a priority for bus routes, will be renewed.