Zoning Bylaw Update
The Government of Alberta has directed the City of Edmonton to amend Zoning Bylaw 20001 by January 22, 2027 (Order in Council, October 22, 2026). The amendments are to focus on the RS-Small Scale Residential Zone, and to make uses, density and height regulations comparable to the regulations under the repealed Zoning Bylaw 12800 (as of December 31, 2023). Additionally, the amendment must include onsite parking space requirements for these lots to be comparable to the parking regulations as they existed on July 1, 2020.
Development applications are reviewed and determined based on the Zoning Bylaw in effect on the date of the decision. Until the Zoning Bylaw is amended, the City of Edmonton must continue to accept and process Development Permit applications per the current regulations within the current Zoning Bylaw 20001.
Given this directive and our service level timelines, it is expected (dependent on volume) that any complete applications received by 11:59pm on November 8, 2026 for development within the RS zone impacted by these changes will be able to be reviewed, and a decision rendered by the Development Authority by the Zoning Bylaw amendment date.
Complete applications using Standardized Designs received by 11:59pm on December 2, 2026 are expected to be reviewed and decisions rendered by the Zoning Bylaw amendment date.
These dates reflect the typical processing times to review applications, but do not consider sharp increases in volume. The dates outlined above do not guarantee that your application will be reviewed and completed prior to the Zoning Bylaw change.
*The above will be updated should new information become available.
Frequently Asked Questions
About the Order
The Government of Alberta has directed the City of Edmonton to amend Zoning Bylaw 20001 within three months from the Order date of October 22, 2026. The amendments are focused on the RS - Small Scale Residential Zone, and to make uses, density and height regulations the same as comparable residential lots or sites under the repealed Zoning Bylaw 12800 (as of December 31, 2023). Additionally, the amendment must include on-site parking space requirements for these lots to be the same as comparable residential lots or sites under repealed Zoning Bylaw 12800 as it read on July 1, 2020.
Reviewing the order, there are two different projects with two different distinct timelines and outcomes: one 90-day project and the other 18 months or less.
To meet the 90-day timeline, we are working on a compressed schedule and provincial defined scope. This means that there will not be an opportunity for public input into the immediate changes. The province has directed that changes are limited to the RS zone in areas related to uses, height, density, and parking.
To satisfy the 18-month requirement, we will begin project planning, scoping resources, and establishing an engagement plan. This work will focus on outcomes to align with the Provincial policy statement on infill development as stipulated in the order.
Planned milestones for first 90 days after order received (October 22, 2026):
- Draft amendments will be posted online as soon as they become available
- December 10-15 - Anticipated timeline for reports and bylaw finalized
- December 28, 2026 and January 4, 2027 - Anticipated advertising dates
- January 22, 2027 - Public hearing required on or before this date
Development for residential areas within the Anthony Henday are primarily regulated by the RS Zone - Small Scale Residential Zone. This covers approximately 49% of the City’s legal parcels.
Based on the clear direction from the Province, and the limited timeframe to draft, finalize, and approve these amendments, there will not be an opportunity for public feedback. Proposed amendments will be shared on the City’s website and social media when available.
Yes - a robust engagement plan will provide opportunities to provide feedback over the coming 18 months.
What Development Will Look Like
Until the Zoning Bylaw is amended, the City of Edmonton must continue to accept and process development permit applications per the regulations within the current Zoning Bylaw. Decisions are made based on the Zoning Bylaw regulations in place on the day of the decision. This means that an applicant may apply under the current regulations, but if the regulations change prior to a decision being rendered, the decision must be made based on the new regulations in place.
Approved Development Permits, including those under construction, can proceed as planned, because they were processed and approved under the current Zoning Bylaw.
An approved development permit is valid for up to two years. During that time, applicants must obtain a valid building permit and start construction for it to remain valid. For Single, Semi-detached and Backyard Houses, the Development Permit is valid for one year, and for larger developments, such as Row Housing development, the Permit is valid for two years (Section 7.190.4.21).
The order requires that the regulations regarding use, density and height are amended to “the same as comparable residential lots or sites” under Bylaw 12800 prior to December 31, 2023. After the Zoning Bylaw has been amended, these regulations will guide the development within the RS Zone, new or existing, that did not receive a decision prior to the amendment date.
Parking Impacts
The order directs Council to amend the Zoning Bylaw to reintroduce the on-site parking minimums in effect as of July 1, 2020. The changes will apply only to the RS -Small Scale Residential Zone. The exact specifications will be available when the draft amendments are shared.
At the June 23, 2020, City Council Public Hearing (item 3.22), City Council voted to enable Open Option Parking city-wide effective July 2, 2020. Open Option Parking removed minimum on-site parking requirements from Edmonton’s Zoning Bylaw. This allowed developers, homeowners and businesses to decide how much on-site parking to provide on their properties based on their particular operations, activities or lifestyle.
The order is focused on parking on private property in the RS Zone and does not impact off-site parking programs. Updates to the City's curbside parking programs will continue to proceed as planned.
The City’s current public engagement on residential parking focuses on residents' experiences and priorities for parking on public residential streets. Engagement is open until November 15. Input from this engagement process will be used to help redesign the Residential Parking program, while shaping the future of the City’s curbside and parking programming overall. Legislative and regulatory factors will be considered as part of Administration's recommendations that will be presented to the Urban Planning Committee in Quarter 1 2027 for consideration and subsequent Council direction.
Process Impacts
Given this directive and our service level timelines, it is expected (dependent on volume) that any complete applications received by 11:59 PM on November 8, 2026, for development within the RS zone impacted by these changes will be able to be reviewed and, most likely, a decision rendered by the Development Authority by the Zoning Bylaw amendment date. Complete applications using Standardized Designs received by 11:59 PM on December 2, 2026, are expected to be reviewed and decisions rendered by the Zoning Bylaw amendment date.
Development applications are reviewed and determined based on the Zoning Bylaw in effect on the date of the decision. Applications will still be reviewed and approved under the current rules until the amendments come into effect in January 2027. Notification and review processes will remain the same.
Development permits will continue to be reviewed and determined based on the Zoning Bylaw in effect on the date of the decision. All application and notification requirements will remain the same.
Specific service level impacts are not known at this time. The November 8 and December 2 deadlines for applications reflect the typical processing times to review applications, but do not consider sharp volume increases that may occur as a result of the order. These application submission dates do not guarantee that applications will be reviewed and completed prior to the Zoning Bylaw change.
Other types of development applications are expected to follow current service levels and will not be impacted by this announcement.
Rezoning applications proceed as usual, with their regular notification and public hearing process. Rezonings will go through the public hearing process, which is required by legislation. Previously approved rezonings remain valid and will not revert back to previous zoning permissions.
Applicants only need to contact their assigned development planner if specifically requested or if they intend to modify their plans. Should an application remain pending past the date the Zoning Bylaw amendments take effect, a Development Approvals representative will contact the applicant to clarify whether they wish to update their application to meet the new regulations or withdraw it entirely. Requests for status updates will not be returned. This allows the development planners to focus on reviewing the application.
Recent Amendments to the Zoning Bylaw
The City has made a number of amendments to improve the RS zone including:
Building Lengths and Facades - On July 8, 2025, the City made amendments to reduce building lengths and improve facade design for midblock developments, which included:
- Maximum building length equal to 25 m or 50% of the lot depth, whichever is less.
- Front facade design with a minimum 15% window area, main entrance door, and a covered entrance feature.
- Minimum of 2 or more design techniques for street-facing facades and side walls regardless of wall length.
- Minimum 1.9 m side setback where an entrance faces an interior side lot line.
- Maximum of 2 side entrances along an interior side lot line.
Building Height - On April 7, 2026, the City made amendments to the RS Zone to decrease maximum building height from 10.5 to 9. 5 metres.
Lodging Houses - On September 22, 2026, the City made amendments to improve how lodging houses are defined, regulated, and enforced. This included:
- Changing the Definition
- Reducing the threshold for a lodging house
- Adding indicators of a lodging house for improved enforcement
- Adding limits to the number of rooms rented in small scale zones
- Prohibiting lodging houses in row houses, multi-unit housing, and secondary suites in small scale zones
Compliance and Enforcement Improvements
The City continues work to implement its Construction Accountability Program, which addresses issues related to construction projects, including infill in mature neighbourhoods. This performance-based program will identify builders with low compliance rates and hold them more accountable through additional oversight and enforcement measures. The program is targeted to launch in Quarter 1 2027. The City has also introduced a number of teams to address construction related issues, including the Coordinated Construction Accountability Team and the Infill Liaison Team. These teams will continue their work as planned.
- Neighbours are encouraged to first try to discuss any concerns with the owner/builder directly to try to resolve the issue if possible.
- If their concerns cannot be resolved and bylaw or legislation infractions are observed, they can reach out to 311 by using the 311 app on a mobile device, submitting a 311 ticket online through the Construction Site Concerns Request form, or calling 311 to have their concerns to have their concerns directed to the appropriate team. Complex construction-practice related concerns and complaints will be directed to the Coordinated Construction Accountability team (CCAT) to provide a coordinated and efficient response.
- The City has developed the Infill in Your Neighbourhood page to help keep Edmontonians informed about what to expect from infill development, the role of the City, builders and neighbours and provide resources to help support residents through the construction process and explain how they can be involved.
- Residents can also sign up to get email notifications about development within 60 metres of their property.
- Edmontonians can learn more at Infill in Your Neighbourhood.
Application Processing Times
Processing times for development, building and land development applications.
Building Permit Application Queue
Application queue time estimates for Building Permit applications.
Select your project to learn about permits, bylaws, applying online and inspections.
Commercial Buildings
Includes non-residential (commercial, industrial, institutional), large scale residential (apartments, row houses with 5 or more units), mixed use (a mix of residential and non-residential) developments, and temporary structures (storage sheds, sea cans).
Residential
Includes new construction and changes to existing single detached houses, semi-detached houses and side-by-side row houses up to 4 units with or without secondary suites, and backyard housing.