Walterdale Bridge Features
Walterdale Bridge replacement project
After more than 100 years, the Walterdale Bridge has reached the end of its service life and needs to be replaced. Construction on the new $155 million replacement project began in 2013. The new bridge will feature three northbound traffic lanes and enhanced pedestrian and cyclist crossings. Roadway and trail links north and south of the river will also be enhanced.
This signature bridge will be the first of its kind in Edmonton, with two 56 m tall arches spanning the river just east of the current bridge. The new bridge arches will be supported by thrust blocks on both river banks, eliminating permanent in-river piers.
Thrust Blocks
Thrust blocks provide a foundation for the arches, which carry the bridge load. Each thrust block requires about 600 cubic metres of concrete installed 20 m below the road elevation.
Building thrust blocks:
- Temporary sheet piling is installed 20 m below the surface. Sheet piling supports deep excavation on both river banks.
- Because a dry environment is needed, sheet piles are designed to connect together. This allows deep excavation within a watertight temporary enclosure, which is called a cofferdam.
- Concrete is poured for thrust blocks.
- After work is complete, the cofferdam is dismantled, and sheet pilings are removed and recycled.
Pedestrian Connections
The new bridge features enhanced pedestrian and cycling facilities, with a separated shared-use path on the east side and a sidewalk on the west side.
These crossings link to the existing south trail network and to a new trail below the north side of the new bridge.
Roads, Pathways, and Landscaping Design
Arches
The signature feature of the new Walterdale Bridge is two 56 m high steel arches (about as tall as the High Level Bridge).
The arches span 206 m and are supported by thrust blocks on both river banks. They angle in towards each other and are connected with steel struts.
Bridge Deck
Cables hang from the arches to support the new bridge deck, which is a steel framework supporting a cast-in-place concrete deck covered with asphalt to make a quieter driving surface.
The existing two-lane bridge is to be replaced by a three-lane bridge. Additional lanes on the new bridge and on the approaching northbound roadways will reduce traffic delays and improve bridge operations and safety.
Abutments
Abutments retain soil on either side of the river and support the new bridge. They are constructed from cast-in-place and precast concrete supported on drilled, cast-in-place concrete piles.
Aterial Roadways
Both Queen Elizabeth Park Road and Walterdale Hill Road will be closed for portions of construction for re-grading and realignment with the new bridge.
One road will be open to traffic during summer construction, and both will be open over the winter. Short-term traffic disruptions and detours are anticipated during final construction.
Traditional Burial Grounds
Rossdale has significant historic and cultural importance. On the north side of river is the Traditional Burial Grounds/Fort Edmonton Cemetery, which includes a memory circle, re-interment area and historic period graveyard. Prior to bridge construction, the site required Historical Resources Act clearance from Alberta Culture, as well as realignment of the legal cemetery boundary and relocation of the site’s interpretive belvedere to a new temporary location.
The new bridge is being built adjacent to the old bridge over an area that has been frequently disturbed throughout Rossdale’s development. This area presents the lowest possibility of finding historic resources during construction.
Walterdale Bridge Historical Resources FAQ
For More Information
Walterdale Bridge Project