Build Phase - Developer Arterial Projects

Powered by Socrata

Once the design has been completed and approved for construction, the project then moves into the Build Phase. The projects in this section will be either awaiting the start of construction or construction is underway. Although the construction is carried out by the Developer, the City takes an active role in monitoring the work being completed to ensure that it adheres to the previously approved design plan and the City of Edmonton Design and Construction specifications.

25 Avenue

25 Avenue: Orchards Gate to Savryn Drive

Under Construction

The extent of this road construction is to construct the first 2 lanes of 25 Avenue from Orchards Gate to Savryn Drive to accommodate growth and increased traffic flows from future subdivision developments. The ACB (asphalt concrete base) is complete however the overlay, sidewalk and shared-use path will be completed in 2015.

Developer Engineer

Brookfield
Dylan Hunchak
780-421-4653
Email

Stantec
Tannis Wisheu
780-969-2236
Email

28 Avenue

28 Avenue SW: 141 Street SW to Hays Ridge Link SW

Detailed Design - Approved for Construction

The extent of this road construction is to construct the third and fourth lanes of 28 Avenue SW from 141 Street to Hays Ridge Link to accommodate growth and increased traffic flows from future subdivision developments. This project is anticipated to be completed in the 2016 construction season.

Developer Engineer

Melcor
Susan Monson
780-945-4810
Email

IBI
Ryan Tomas
780-428-4000 x 203
Email

28 Avenue: Chappelle Blvd to future west collector

Detailed Design - Approved for Construction

The extent of this project is to construct the first two lanes of 28 Avenue from Chappelle Boulevard to a future collector road west further west. This project is anticipated to be completed in the 2016 construction season.

Developer Engineer

Brookfield Residential

Stantec

30 Avenue

30 Avenue SW: Cavanagh Drive to 103A Street

Under Construction

The extend of this road construction is to construct the first 2 lanes of 30 Avenue from Cavanagh Drive to 103A Street to accommodate growth and increased traffic flows from future subdivision.

This project is anticipated to be completed in November 2015.

Developer Engineer

Blackmud Trading
Wade Zwicker
780-425-7361
Email

Stantec
Rick Prentice
780-917-7035
Email

30 Avenue SW: Blackmud Creek to Cavanagh Drive

Under Construction

The extent of this road construction is to construct the first 2 lanes of 30 Avenue from Blackmud Creek to Cavanagh Drive to accommodate growth and increased traffic flows from future subdivision developments.

The road construction from Cavanagh Drive to 111 Street has been completed. The remainder portion from 111 Street to Blackmud Creek is anticipated to be completed in the 2016 construction season.

Developer Engineer

Blackmud Trading
Wade Zwicker
780-425-7361
Email

Stantec
Rick Prentice
780-917-7035
Email

34 Street

34 Street - 153 Avenue to 158 Avenue

(Storm Sewer Offsite Installation from 153 Avenue to 167 Avenue)

Under Construction

The extent of the roadway construction from 153 Avenue to north of 158 Avenue includes the reconstruction of 34 Street from a rural roadway to an urban collector standard. This entails the construction of a two lane each way roadway with curb and gutter, separate walk, transit bus stop pads and accesses.

The extent of the roadway construction from north of 158 Avenue to 167 Avenue includes the reconstruction of the rural roadway due to the installation of a storm sewer line that will connect to the McConachie Neighbourhood storm water infrastructure.  This portion of the work has been completed.

Developer Engineer

Albari Holdings Ltd.
Manning Commercial Project

McConachie Communities Investments Ltd
McConachie Stage 8 Project

Wade Zwicker
(780) 425-7361
Email

Stantec Inc.

41 Avenue

41 Avenue SW: Blackmud Creek to James Mowatt Trail

Under Construction

The extent of this project is to construct first two lanes of 41 Avenue from Blackmud Creek to James Mowatt Trail in order to accommodate growth and increased traffic flows from future subdivision developments.

The road is open to traffic. The remaining work includes the construction of the shared used path and landscaping.

Developer Engineer

MLC

Stantec

50 Street

50 Street - Ellerslie Road to 14 Avenue SW

Under Construction

The extent of this road construction is to construct 2 urbanized lanes of 50 Street from Ellerslie Road to 14 Avenue SW to accommodate growth and increased traffic flows from future subdivision developments.

This work is under construction. Lane closure is anticipated in 2015. Grading and underground work is currently in progress. The project is anticipated to be complete at the end of December 2015.

Developer Engineer

Cameron/MLC
Otto Hedges
780-420-0044
Email

Stantec Inc.

109 Avenue

109 Ave - TUC to 205 Street

Under Construction

The extent of this road construction is to construct the first 2 lanes of 109 Avenue from the TUC to 205 Street to accommodate growth and increased traffic flows from future subdivision developments.

The underground installation at this intersection and intersection re-construction at 199 Street was completed by June 2015. The road has been paved. The work that is still required to be completed are the installation of the streetlights, bus pads and shared used path, This work is anticipated to be completed in the 2016 construction season.

Developer Engineer

Walton International Group

Select Engineering
Frank Vespi
(780) 651-5792
Email

156 Street

156 Street - North of 137 Avenue (Mistatim)

Completed

The extent of this road construction was to construct a southbound left turn bay on 156 Street, a multi-use trail on the east side of 156 Street from 137 Avenue to the north boundary of the subdivision, and a bus stop pad and connector sidewalk. This project is now complete.

Developer Engineer

Pinnacle International (St. Albert) Lands Corp.

Sameng Inc.

215 Street/Winterburn Road

215 Street: Glastonbury Blvd - 62 Avenue

Under Construction

The extent of this road construction is to construct the first 2 lanes of 215 Street from Glastonberry Boulevard to 62 Avenue to accommodate growth and increased traffic flows from future subdivision developments.

The road is open to traffic. The right turn bay and shared used path is anticipated to be completed in the 2016 construction season.

Developer Engineer

Aldritt Development

IBI Group

215 Street - 112 Avenue to Yellowhead Trail

Under Construction

The extent of this project is to construct the first two lanes of 215 Street from 112 Avenue to Yellowhead Trail to accommodate growth and increased traffic flows from future subdivision developments.

This project is anticipated to be completed in the 2016 construction season.

Developer Engineer

Walton International Group

Stantec Inc.

Ellerslie Road

Ellerslie Road: 50 Street to Pioneer Meadow Entrance (34 Street)

Under Construction

The extent of this road construction is to construct the first 2 lanes of Ellerslie Road from 50 Street to Pioneer Meadow Entrance (34 Street) to accommodate growth and increased traffic flows from future subdivision developments.

Grading and underground work is in progress. Full road closure will require during full swing of construction work in 2015. The project is scheduled to be completed in December 2015.

Developer Engineer

Beaverbrook
Al Kulay
(780) 484-4389
Email

Stantec Inc.
Jim Merkle
780-969-3223
Email

Ellerslie Road - 127 Street - 141 Street

Under Construction

The extent of this project is to construct the first two lanes of Ellerslie Road from 127 Street to 141 Street in order to accommodate the growth and increased traffic flows from future developments. 

This project is anticipated to be completed in the 2016 construction season.

Developer Engineer

MLC
Otto Hedges
780-420-0044
Email

Stantec
Jim Merkle
780-969-3223
Email

For More Information