Bridge Removal & Replacement - Over Blackmud Creek at 111 Street and at 30 Avenue SW


About the Project
The City identified the 111 Street Bridge over Blackmud Creek as having reached the end of its service life. The bridge was removed and the crossing reclaimed.
The 30 Avenue Bridge over Blackmud Creek has also reached the end of its service life and required replacement. The approved concept plan for 30 Avenue SW was for a 4 lane configuration; however, due to traffic volumes, only two lanes were constructed at this time.

![]()
Where We Are Today
This project began in October 2012 and was completed in fall 2013.
The scope of work for the 111 Street over Blackmud Creek bridge, included:
- Removal of the existing 111 Street bridge – a 3-span structure with a timber substructure and a precast concrete superstructure.
- Reclamation of the bridge site with an appropriate landscape design.
- Closure of the road right of way.
The scope of work for the 30 Avenue Bridge over Blackmud Creek, included:
- Construction of a new 42m long single span bridge on the approved new 30 Avenue SW alignment.
- Construction of a 3m wide Shared Use Path on and under the new 30 Avenue bridge.
- Construction of a 7m wide wildlife corridor under the new 30 Avenue bridge.
- Removal of the existing 30 Avenue bridge – a 3 span timber trestle.
- Reclamation of the bridge removal and reconstruction sites with an appropriate landscape design.
Timeline
Construction began with earthwork in October 2012. Bridge construction and completion of the 30 Avenue Bridge over Blackmud Creek was carried out during the 2013 construction season.
Project History
July 2013 - Construction Update
- Roadway construction began the week of June 24.
- The bridge deck, approach slabs, and barriers have been poured.
- The existing 30 Avenue SW Bridge over Blackmud Creek was closed on July 12 and is expected to reopen when the new replacement bridge opens to traffic August 1. Once the new bridge is open, crews will begin demolishing the old 30 Avenue SW Bridge and 111 Street Bridge over Blackmud Creek.
Traffic Flow Notification - July 12, 2013
June 2013 - Construction Update
- The bridge deck, approach slabs, and barriers have been poured and the roadway construction began the week of June 24.
- Inclement weather has caused minor delays however it should not affect the anticipated re-opening for later in the summer.
- Once the new bridge and roadway connections are complete, the council approved removal of the existing bridges at 111 Street and at 30 Avenue will begin.
February 2013
On Tuesday, February 26, 2013, City representatives gave detailed information regarding the design and construction of the removal and replacement of the Blackmud Creek bridges. Below are the presentation materials as well as any information that was distributed and displayed.
For More Information
Ryan Teplitsky
| Telephone | 780-944-7651 |
|---|---|
| ryan.teplitsky@edmonton.ca |