Popular Searches
  • Big Bin Events
  • Canada Day
  • Eco Stations
  • Pay Tickets
  • Permits
  • Property Taxes
  • Spray Parks

Contact Us Visiting?

215 Street Upgrade

About the Project

215 Street was upgraded to 2 urbanized lanes; south of Webber Greens Drive to north of Whitemud Drive. The upgrade will accommodate the growth and increased traffic flows from future developments.

Construction Includes:

  • 215 Street (Webber Greens Drive to Whitemud Drive) upgraded to 2 urbanized lanes
  • Shared Use Path along the east side of 215 street
  • New street lighting
  • New right turning geometry
  • Curb and gutter improvements 

Timeline and Funding

Construction began in May 2011 and is now complete.

The 215 Street Widening was funded and managed exclusively by an independent developer, Melcor Developments Ltd, and its consultant, AECOM Canada Ltd.

When an independent developer begins a residential or commercial project they also develop the roadways to accommodate any traffic impact from the future development. These projects are funded and managed exclusively by the developer. It is the City of Edmonton’s responsibility to ensure the developers are complying with the approved standards and specifications. 

For More Information

Loli Fernandez

Transportation Planning

Title Project Engineer
Telephone

780-944-7683

Email Loli.Fernandez@edmonton.ca