127 Street Reconstruction - Project History

Construction Notice - April 22, 2016

Construction on 127 Street will take place between May and October 2016. See map below for construction staging.

Stage One of construction started on Sunday, May 1:

  • Both southbound lanes are closed and northbound traffic is reduced to one lane for the next three months
  • Detour using 121 Street or St. Albert Trail
  • All bus stops on 127 Street are closed until October 2016. See www.takeETS.com for detour information and schedules
  • Free shuttle (route 398) through Sherbrooke and Prince Charles started running April 24

Please Note: Traffic barriers across 124 Street at 123 Avenue will remain in place as part of the Prince Charles Community Traffic Management Plan. The implications of reinstating 124 Street as a detour, even temporarily, are significant for Prince Charles, as it would see a return of 4000-6000 vehicles per day, as well as additional detour traffic adjacent to the neighbourhood park and residential properties during the summer months when more people are out and about. 

  • Please detour using St. Albert Trail, 121 Street, 142 Street, 149 Street and 97 Street. 
  • Street signs are in place to direct parents to the three schools in the area during construction.

Information Session - April 6, 2016

On Wednesday, April 6, City representatives held an Open House to provide project details and to have the project team answer questions about the reconstruction.

Meeting Materials:

Presentation

Display Boards

Final Design Plan

Fact Sheet

Approved Concept Plan

127 Street Reconstruction approved plan is available for review.

Approved Concept Plan - 118 Avenue to 122 Avenue

Approved Concept Plan - 121 Avenue to Yellowhead Trail

Highlights of the plan include:

  • 4 travel lanes are maintained and widened to current design standards
  • Addition of a full traffic signal at 122 Avenue for increased safety
  • Full reconstruction of the roadway
  • East sidewalk reconstruction

The project team provided an update on this project to City Council’s Transportation Committee on May 27, 2015. The report outlines the progress of the concept plan for the reconstruction of 127 Street between 118 Avenue and Yellowhead Trail, as well as how residents’ concerns with speeding and shortcutting through the adjacent communities may be addressed.

Open House - January 28, 2015

The City of Edmonton held an Open House to present the recommended concept plan for improvements to 127 Street between 118 Avenue and Yellowhead Trail. Below is the information presented at the Open House.

Meeting Materials:

Presentation

Display Boards

What We Heard - March 2015

Open House - October 16, 2014

The City of Edmonton held an Open House to present two concept plans for improvements to 127 Street between 118 Avenue and Yellowhead Trail. Below is the information presented at the Open House.

Meeting Materials

Presentation

Display Boards

Fact Sheet- October 2014

What We Heard - December 2014

Online Survey – August 15–September 15, 2014

An online survey asked for information about local experience with this section of the roadway. 304 local residents, commuter and representatives from local organizations and business voiced their concern over congestion, narrow travel lanes and other local issues.

Online Survey Summary - What We Heard

For More Information

Joleen Harris

Transportation Planning

Title Senior Engineer
Telephone

780-944-7659

Email joleen.harris@edmonton.ca