Metro Line (NAIT to North City Limits) Project History

Determining How the LRT Will Fit

Project Lifecycle Concept

January 2010 to May 2013

Metro Line: NAIT to North City Limits On Hold

May 8, 2013

Currently no budget has been allocated to this project to continue the Metro Line: NAIT to North City Limits to the next stages of preliminary engineering, design and construction.

City Council sets the priorities for LRT construction and determines how funding will be used, however the City's 30-year Transportation Master Plan includes extending LRT to all sectors of the City by 2040.

Council Approved Metro Line: NAIT to North City Limits Concept Plan

May 1, 2013

Transportation Committee approved the Metro Line: NAIT to North City Limits Concept Plan with two subsequent amendments.

The concept plan was developed with input from the public. It defines where the LRT will run along the approved route and where LRT stations will be located.

Transportation Committee Meeting Minutes from May 1, 2013 (Item 6.1)

Concept Planning Study Metro Line: NAIT to North City Limits Transportation Committee – May 1,2013

Recommended Concept Plan Booklet 

Design Changes to the 153 Ave Corridor Public Meeting

April 3, 2013

Participants learned about the design changes to the 153 Avenue corridor of the Metro Line: NAIT to North City Limits concept plan prior to presentation to City Council. Modifications to the recommended concept plan were presented and explained.

Meeting Materials

Display Boards

Presentation

Stations

Recommended Concept Plan Presented - Public Meetings

Dec 5 & 6, 2012

The plan was developed with input from the public. It defines where the Metro Line: NAIT to North City Limits will run along the approved route and where LRT stations will be located.

Recommended Concept Plan - Booklet

Meeting Material

Presentation

Display Boards

Topics of Interest

What We Heard

Property Value and Acquisition

Detailed Maps

Campbell Road

137 Street

127 Street

Castle Downs

145 Avenue

137 Avenue

132 Avenue

City Centre Redevelopment North

City Centre Redevelopment South

Draft Concept Plan Presented for Feedback - Public Meetings

Sept 26 & 27, 2012

Opportunities were given for feedback on the draft concept plan, which was developed with input received at previous public meetings.

Metro Line: NAIT to North City Limits Draft Concept Plan

Presentation

What We Heard (Sept 2012)

Display Boards

Northwest LRT Display Boards

127 Street Station

132 Avenue Station

137 Avenue Station

137 Street Station

145 Avenue Station

Campbell Road Station

Castle Downs Station

City Centre Redevelopment North Station

City Centre Redevelopment South Station

Discussing Options - Open Houses

June 19 & 20, 2012

For More Information

Future LRT General Inquiries

Telephone 780-496-4874