Project and Construction Timelines

Project Timeline
- Concept design—2013/2014
- Preliminary design completion—2014
- Construction start — July 2015
- Construction completion—anticipated fall 2016
Construction Updates

The majority of construction work for the West End Trails is complete, and the south trails are open for the public to use and enjoy! Seasonal work and construction of sections of the trails near the Terwillegar Park Footbridge will be complete in 2016.
The new trails in Terwillegar Park and River Valley Oleskiw will join the existing trail network and will eventually be connected by the Terwillegar Park Footbridge. These trails are an essential component to achieve connectivity within the river valley.