The Build
Construction on Rogers Place began March 2014, and is scheduled to be done in fall 2016. Watch the construction activity with the Rogers Place construction camera.
Overnight and Weekend Road Closures, 104 Avenue, 101 St - 103 St
104 Avenue will continue to be closed overnight Monday to Friday and on occasional weekends until the construction of Rogers Place is done in fall 2016.
Please detour using Jasper Avenue or 107 Avenue.
The closures are necessary to allow for the safe installation of the Winter Garden pedway over 104 Avenue, with minimal disruption to traffic. The City has issued a noise bylaw relaxation to PCL Construction to allow crews to work beyond the standard time regulations.
The January 8, 2016 Construction Bulletin details the road closures and area traffic movements.
Exterior work continues
The construction of Rogers Place started at a brisk pace and continues to move rapidly.
The steel beam and exterior structure is now completed. Crews have now begun the exterior finishing work, including the stainless steel tiles that will give Rogers Place its iconic finish that resembles snow drifts.
Much of the work is now focused within the building, with drywall and preparation of the future ice surface underway.
Previous Construction Notices
June 3, 2015 Construction Bulletin: Steel and exterior work underway
January 2, 2015 Construction Bulletin: Overnight closures of 104 Avenue
September 23, 2014Construction Bulletin: Structural steel work starts
February 28, 2014 Construction Bulletin: Excavation starts on site.
July 29, 2013 Construction Bulletin: Pile testing on site, completed mid-October 2013.
The Before
Aerial view of the site before construction started in March 2014: