Johnny Bright Sports Park Development
In 2005, a feasibility study was completed to explore the redevelopment of Jasper Place Fitness and Leisure Centre into a multi-purpose facility. The study was updated in 2011 and the project phased to address lifecycle deficiencies. The first phase of the project will include renewal of the fitness and leisure centre, a transition into the St. Francis Xavier Sports Centre, and renewal of the Jasper Place Bowl grandstand.

Information Session
Wednesday, May 11, 9-11am
Wednesday, May 11, 6-8pm
Jasper Place Fitness & Leisure Centre
9200 163 Street NW
The information sessions will provide:
- Project Scope Updates
- Project Timelines
- Proposed building design for Phase 1
- Opportunity to provide feedback (Survey)
Please note: there will be no formal presentations.
Feedback Survey

Project Timeline

| Future | Phase II design and construction, pending funding approval. |
| Spring 2018 | Jasper Place Bowl opens. |
| Winter 2018 | Jasper Place Fitness and Leisure Centre opens. |
| 2016 - 2018 | Construction of Phase I. |
| 2016 | Design of Phase I. |
| 2014 | City Council approves funding for Phase I for the renewal of the Jasper Place Fitness & Leisure Centre and the renewal of Jasper Place Bowl Grandstand as part of the 2015 – 2018 capital budget. |
| 2009 - 2011 |
A facility condition assessment report was completed on the Jasper Place Bowl Grandstand. The Jasper Place Facility Expansion Feasibility Study was completed to guide the development of the integrated multi-purpose facility and address facility deficiencies and lifecyle challenges in a phased approach. Jasper Place Fitness and Leisure Centre Feasibility Study (February 2011) |
| 2007 | Public consultation to determine facility uses and preferred future development through telephone, online, paper, and one-on-one surveys. |
| 2007 | The 2007 City Council approved Medium Term Recreation and Sports Field Plan identifies the expansion of the Jasper Place Fitness & Leisure Centre and the renewal of Johnny Bright Sports Park. |
Project Overview
In 2005, a feasibility study was completed to explore the redevelopment of Jasper Place Fitness & Leisure Centre into a multi-purpose facility. The study was updated in 2011 and the project was split into two phases.
City Council approved funding for phase I in the 2015-2018 capital budget. This phase addresses lifecycle deficiencies including the replacement of the pool deck drainage system, windows, ceiling in the natatorium, structural and waterproofing repairs, retrofit to the aquatic change rooms and exploration of the development of the family change rooms as identified in the feasibility study.
Phase I also includes the transition of the fitness centre to St. Francis Xavier Sports Centre.
In addition to phase I, the Jasper Place Grandstand will be replaced to include dressing rooms, officials rooms, concession and a spotter’s box.
Phase II, which is currently unfunded, includes the integration of Jasper Place Fitness & Leisure Centre, Bill Hunter Arena and Jasper Place Annex into a multi-purpose facility to include the addition of new fitness centre, studios and locker rooms, whirlpool, multi-purpose rooms, child play space, administration, lobby and required parking.
For More Information
Program & Project Development
PO Box 2359
12th Floor CN Tower
Edmonton, AB T5J 2R7
| Telephone |
In Edmonton: 311 Outside Edmonton: 780-442-5311 |
|---|---|
| CMSParkAndFacilityDevelopment@edmonton.ca |
