Argyll Park Plan
Project Overview
The City of Edmonton is working on three integrated initiatives for Argyll Park.
- Proposed Argyll Park Master Plan
- Proposed redevelopment of the Argyll Velodrome in partnership with the Argyll Velodrome Association
- Proposed future use of the Argyll School surplus site
The master plan underwent public consultation, including a public open house in the community on September 24, 2007. Feedback from the open house is posted below.
The master plan is currently being modified to address community comments and concerns. The master plan will be presented to City Council in early 2008.
Proposed Argyll Park Master Plan
Open House Feedback Summary - Argyll Park Master Plan
Open House Feedback Comments - Argyll Park Master Plan
Proposed Argyll Velodrome Redevelopment
Open House Feedback Comments - Velodrome Redevelopment
Project Timeline

| October 2013 | Landscaping of topsoil and sod (weather permitting) |
|---|---|
| September/October 2013 | Demolition of Argyll School, removal of debris and backfill of excavation site |
|
2008 |
Presentation of Master Plan to council. |
| September 2007 | Public Open House Consultation Presented the master plan for open house for feedback. |
For More Information
Program & Project Development
PO Box 2359
12th Floor CN Tower
Edmonton, AB T5J 2R7
| Telephone |
In Edmonton: 311 Outside Edmonton: 780-442-5311 |
|---|---|
| CMSParkAndFacilityDevelopment@edmonton.ca |