Southwest Community Recreation Centre and Leger Integrated Site Project Update
October 19, 2009
Leger District Park Site
- Tree planting on Leger Road and the sports fields adjacent to Lillian Osborne High School is complete.
- The sidewalk from the west end of the Leger Transit Centre to the Lillian Osborne High School will be constructed this fall.
- Construction of the sports fields in the NW corner of the site has begun and should continue for several weeks.
Recreation Centre Complex
- The Recreation Complex foundation walls, grade beams and slabs are 95% complete. Structural steel installation is over 90% complete. Roof deck is being installed over the structural framing.
- Masonry work has begun, with exterior steel stud work at 15% completion.
- The leisure/wave pool floor has been poured. Work on building mechanical, electrical and pool system rough-ins continues.
- Site work for the parking areas is underway. The drop off loop is now open for access to Lillian Osborne High School. The concrete walkway from the Recreation Centre to the Leger Transit Centre has been poured.
- The Recreation Complex is scheduled to open in the fall of 2010.
Arena Complex
- The Development Permit and Structural Foundation Permit approvals have been received. Application has been made for the Building Permit.
- Foundation work is 60% complete, with floor slabs between Rink 1 and Rink 2 at 80% completion. Elevator shaft formwork continues. Structural steel framing is scheduled to begin in mid November.
- The Arena Complex is also scheduled to open in the fall of 2010.